ITH - Intl. Tower Hill Mines - WKN A1C4CG

The Northern Miner Daily News
August 3, 2010
Tower Hill doubles Livengood mine life, output in new PEA
Vancouver - International Tower Hill Mines' (ITH-T) Livengood project in Alaska could produce half a million ounces of gold annually for 21 years, according to a new and improved preliminary economic assessment (PEA).
Tower Hill completed a PEA for Livengood last year, but that study only assessed the potential to turn the oxide portion of the deposit into a heap-leach operation. Now the company has incorporated the large sulphide gold deposit into the economic study by adding a large milling and flotation circuit in the fourth year of operations.
The Money Knob deposit at Livengood is a near-surface, tabular gold zone that is almost perfectly suited to open pit mining. An open pit frame encompasses 600 million indicated tonnes grading 0.65 gram gold per tonne plus 48 million inferred tonnes averaging 0.64 gram gold, which represents almost three-quarters of the overall resource defined to date.
To mine the pit requires a strip ratio of just 1 tonne of ore to 1.07 tonnes of waste. For the first three years the operation would only tap into the oxidized rock, sending 100,000 tonnes of ore to be crushed and dumped on a valley-fill heap leach pile every day. In year four the mill and flotation circuits would come on line; at that point throughput to the heap leach would drop to 35,000 tonnes daily while the mill would start churning through 53,400 tonnes a day.
With metallurgical recoveries of 81% for the mill-float circuit and 76% for the heap leach, Tower Hill expects to produce 504,000 oz. gold annually from Livengood. By the end of its 21-year lifespan the operation have recovered 10.6 million oz. gold from the Money Knob deposit.
To build the first stage of the project, which encompasses the heap leach facilities and all supporting mine infrastructure, is expected to cost US$635 million. Once the heap leach operation is up and running, Tower Hill would then need to invest another US$750 million to build the sulphide processing circuit. Combined, the full operation requires an investment of almost US$1.4 billion.
For that investment, Tower Hill should be able to produce an ounce of gold for US$560. Using a gold price of US$950 per oz., the Livengood project carries a net present value (NPV) of US$813 million, using a 5% discount rate, and should generate a 15.4% internal rate of return (IRR). Boosting the price of gold to US$1,200 per oz. lifts the NPV to US$2.3 billion and the IRR to 32.5%.
Tower Hill says it will now investigate several possibilities to increase the project's value. The company will look at increasing throughput rates to increase production and take better advantage of economies of scale, improving the mining sequence to reduce operational costs, and adding certainty to cost estimates to reduce to 25% contingency included in the cost prediction.
And Tower Hill is by no means finished exploring at Livengood. The Money Knob deposit remains open to the west, to the southeast, and at depth. The company's current drill campaign is focused on expanding the higher-grade Southwest zone, confirming the inferred resource extrapolation at depth, and infilling the drill pattern to upgrade the small portions of the Main and Sunshine zones that are still only inferred.
The deposit currently covers 3 sq. km. The gold-in-soil anomaly that initially led Tower Hill to the deposit, however, stretches across 12 sq. km, of which only half has been drill tested.
The Money Knob deposit is hosted in a thrust-interleaved sequence of sedimentary and volcanic rocks. Gold is related to a 90-million year old dike swarm that cuts through the thrust stack. The net result is broad, flat-lying zones of stratabound mineralization around more vertically-continuous, higher-grade core zones.
Tower Hill has already started work on a pre-feasibility study for Livengood, with hydrological studies, facility location studies, geotechnical studies, and environmental baseline data collection underway. The company is also continuing with metallurgical testwork in hopes of further optimizing recoveries.
The project, which all in is home to 789 million indicated tonnes grading 0.62 gram gold per tonne plus 229 million inferred tonnes averaging 0.55 gram gold for 19.7 million oz. gold, is located 110 road kilometers north of Fairbanks, along the paved Elliot Highway.
On news of the new PEA Tower Hill's share price gained 12
 
EALTALK-More gold M&A to come after Kinross,bankers say

Mon Aug 9, 2010 2:59pm GMT

*Potential buyers include Canada's top gold producers

*Potential targets include nearly a dozen midcaps

*Cheaper to buy than to build new mines (Figures in U.S. dollars, unless noted)

ByPav Jordan and Euan Rocha

TORONTO,Aug 9 (Reuters) - A $7.1 billion bid for Red Back Mining (RBI.TO), aCanadian-based company active in Africa, has a stable of other mid-tiered gold minersdreaming of similar takeover approaches from larger rivals.

KinrossGold Corp (K.TO) made the all-stock offer on Aug. 2, saying Red Back's twomines would help propel its annual output to about 2.6 million ounces by theend of 2010 and about 3.9 million ounces by 2015, making it a comfortabletop-tier gold producer.

Theexpected output acquired in the deal, though well below the nearly 7.5 millionounces a year produced by No.1 Barrick Gold (ABX.TO), would put Kinross closerto rivals like Newmont Mining (NEM.N), with more than 5 million ounces, andGoldcorp Inc (G.TO), at around 2.4 million ounces.

"Certainlythe others have to be asking themselves: 'Have I constructed the list ofcompanies that I want? Have I done sufficient due diligence and am I ready togo out and make a purchase here?'" said Adam Graf, an analyst with DahlmanRose in New York. "And: 'If I wait any longer are the prices going to bebid up, or am I going to lose my opportunity?'"

Candidateswho might look for growth through acquisition could include companies likeBarrick, Goldcorp, Agnico Eagle (AEM.TO) or Yamana Gold (YRI.TO), to name ahandful.

Thelist of companies who might be attractive takeover targets is even longer,including Guyana Goldfields (GUY.TO), Exeter (XRC.TO), International TowerHill (ITH.TO), Vista Gold Corp (VGZ.A), Osisko (OSK.TO), Detour (DGC.TO),Seabridge (SEA.TO) and NovaGold (NG.TO). All of them have big projects thatmight fit better in the portfolios of larger companies.

"I'mwaiting for the big flurry, I still don't think we've seen it," said Graf.

Investmentbankers at Canada's BMO Capital Markets, a unit of the Bank of Montreal(BMO.TO) and which leads league tables in gold mining deals this year, say alot of it comes down to timing.

^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^

TopGold M&A Advisors: link.reuters.com/sap93n

^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^

TheKinross deal comes at a moment in the production cycle where new producers areemerging after years of drilling, and larger companies need to replacedwindling reserves.

Italso comes at a time when the price of gold is at all-time highs, and the costsof building mines from scratch has skyrocketed along with the high prices ofcommodities and even labor.

"Ifyou think of the build-versus-buy decision that executives typically facebefore they do an M&A ... the impetus and the reason to buy has shifted tobuy-versus-build," said Andre Hidi, who heads the global mergers andacquisitions group at BMO, the lead adviser to Kinross in the Red Back deal.

BMOcould not comment directly on the deal, but Egizio Bianchini, an investmentbanker and the head of global metals and mining investment for the firm, saidchief executives at gold companies have been confident of the strength of themarket for some time, even before analysts became comfortable with today'sprices.

"We'reat a stage now where there's a very robust number of companies that are lookingto put mines into production, probably about as robust a roster as we've had ina long time," said Bianchini.

"It'san environment that right now, for most companies, is conducive to M&Aactivity," he said.

TheKinross deal was the latest of at least three major deals in gold mining so farthis year.

Aroundthe time Red Back shareholders are voting on Kinross' offer, Australia'sNewcrest Mining (NCM.AX) will complete an $8 billion acquisition of local rivalLihir Gold (LGL.AX) to create the world's No. 4 listed gold miner.

Atleast four other top gold companies also looked at the Lihir books, sourceshave said, including AngloGold Ashanti (ANGJ.J), Barrick and Newmont.

ForPeter Marrone, chief executive at Yamana Gold, more consolidation will likelyoccur as stock valuations at larger companies improve.

"Whatwe've seen over the past year is a significant share price appreciation of thesmaller companies, the juniors and development stage companies, but not yet forthe more senior companies," he told Reuters. "As that paradigmshifts, and it will shift, I believe there will be a buying opportunity andconsolidation in the industry."

Thesweet spot?

Themain players say keep your eye out for takeovers in the $500 million to $2.5billion range.

(Editingby Frank McGurty)
 
International Tower Hill Shareholders Approve Corvus Gold Inc. Spin-out

VANCOUVER, BRITISH COLUMBIA--(Marketwire - Aug. 13, 2010) - International Tower Hill Mines Ltd. ("ITH" or the "Company") (TSX:ITH)(NYSE Amex:THM)(FRANKFURT:IW9) is pleased to announce that its shareholders have voted 99.85% in favour of approving the spin-out of its Alaska and Nevada exploration assets into Corvus Gold Inc. ("Corvus") by way of a plan of arrangement. Over 54% of the outstanding shares of the Company were represented and voted on the arrangement resolution at the Company's Special Meeting held on August 12, 2010.

Jeff Pontius, the President and CEO of the Company, noted that "I am extremely pleased at the overwhelming approval for the Corvus spin-out received from the Company's shareholders. The completion of the arrangement will allow ITH to focus all of its energies on the ongoing development of the Livengood Project. Corvus, as a separate and independent company, will be able to focus on generating value from the Company's current Alaska and Nevada exploration projects through the further exploration of those projects, as well as utilizing our extensive Alaska database to identify and acquire additional prospective projects."

As the next step in the process, an application for a final order of the Supreme Court of British Columbia approving the arrangement will be set down for hearing before the presiding Judge or Master in Chambers at the Courthouse at 800 Smithe Street, Vancouver, British Columbia, on August 20, 2010 at 9:45 a.m., or so soon thereafter as counsel may be heard.

The Company is also pleased to report that Corvus has received the conditional approval of the Toronto Stock Exchange ("TSX") to list the common shares of Corvus on the TSX. Listing of the common shares is subject to the completion of the arrangement spin-out and compliance with all of the TSX requirements, including receipt by the TSX of all required documentation by October 26, 2010.

About International Tower Hill Mines Ltd.

International Tower Hill Mines Ltd. is a resource exploration company, focused in Alaska and Nevada, which controls a number of exploration projects representing a spectrum of early stage to the advanced multimillion ounce gold discovery at Livengood. ITH is committed to building shareholder value through new discoveries while maintaining a majority interest in its key holdings, thereby giving its shareholders the maximum value for their investment.

On behalf of INTERNATIONAL TOWER HILL MINES LTD.

Jeffrey A. Pontius, President and Chief Executive Officer

This press release contains forward-looking statements within the meaning of Section 27A of the Securities Act and Section 27E of the Exchange Act. All statements, other than statements of historical fact, included herein including, without limitation, statements regarding the anticipated completion of the arrangement spin-out involving the Company and Corvus Gold Inc. and the listing of the common shares of Corvus on the TSE, are forward-looking statements. Although the Company believes that such statements are reasonable, it can give no assurance that such expectations will prove to be correct. Forward-looking statements are typically identified by words such as: believe, expect, anticipate, intend, estimate, postulate and similar expressions, or are those, which, by their nature, refer to future events. The Company cautions investors that any forward-looking statements by the Company are not guarantees of future results or performance, and that actual results may differ materially from those in forward looking statements as a result of various factors, including, but not limited to, the failure of the Company and Corvus to obtain the final order approving the arrangement or to satisfy the conditions precedent top the listing of the Corvus shares on the TSE. Other risks and uncertainties are disclosed in the Company's annual information form filed with Canadian securities commission and its annual report on Form 40-F filed with the United States Securities and Exchange Commission, and other information released by the Company and filed with the appropriate regulatory agencies. All of the Company's Canadian public disclosure filings may be accessed via www.sedar.com and its United States public disclosure filings may be accessed via www.sec.gov, and readers are urged to review these materials, including the technical reports filed with respect to the Company's mineral properties.

NR10-25



For more information, please contact

International Tower Hill Mines Ltd.
Quentin Mai
Vice-President - Corporate Communications
1-888-770-7488 (toll free) or (604) 683-6332
(604) 408-7499 (FAX)
qmai@internationaltowerhill.com
www.internationaltowerhill.com
Click here to see all recent news from this company
 
International Tower Hill Reports Latest Results from 22 Drill Holes at the Expanding Livengood Gold Deposit, Alaska

http://www.marketwire.com/press-rel....ngood-TSX-ITH-1305632.htm

VANCOUVER, BRITISH COLUMBIA--(Marketwire - Aug. 17, 2010) - International Tower Hill Mines Ltd. (TSX:ITH)(NYSE Amex:THM)(FRANKFURT:IW9) -

Highlights

MK-RC-0382: 61.0 m @ 2.65 g/t gold – Sunshine Infill
MK-10-53: 5.2 m @ 6.75 g/t gold & 34.8m @ 1.29 g/t gold – Core Zone Infill
MK-RC-0378: 41.2 m @ 1.27 g/t gold & 219.5m @ 0.94 g/t gold – Sunshine Infill
MK-RC-0380: 21.3 m @ 1.73 g/t gold & 44.2m @ 1.30 g/t gold – New Olive Area
MK-RC-0373: 48.8 m @ 1.92 g/t gold (bottom of the hole) - Sunshine Infill
MK-10-55: 36.3 m @ 1.53 g/t gold

– Core Zone Infill International Tower Hill Mines Ltd. ("ITH" or the "Company") is pleased to announce the results from the latest 22 drill holes completed in its 50,000-metre Summer 2010 Livengood Exploration Program. The Summer 2010 drill program is focused on converting resources to the measured and indicated categories through infill drilling, as well as step-out resource expansion and testing of "new deposit" exploration targets within the overall district. Significantly, the project continues to expand as a new area of interest to the southwest of the Core Zone, named the "Olive Zone", has been identified. The Company is currently operating five drills at Livengood (three RC and two core rigs) and anticipates adding a sixth in the near future.

Highlights of these recent results include:

The Money Knob deposit at Livengood continues to expand at depth, as demonstrated by recent infill drilling results in the Sunshine Zone (MK-RC-0373, 49 m @ 1.9 g/t gold below 350 metres and MK-RC-0376, 15 m @ 1.2 g/t below 360 metres);
A new area of deposit expansion, named the "Olive Zone", is emerging to the southeast of the Core Zone (MK-RC-0380, 21 m @ 1.7 g/t gold and 44 m @ 1.3 g/t gold); and
The "5 spot" infill program continues to favourably compare with the surrounding holes, confirming and, overall, upgrading the prior drilling results. The Company anticipates that the results of this infill program will enable the current estimated indicated and inferred resource ounces to be "upgraded" to the measured and indicated, respectively, categories.
Jeff Pontius, President and CEO, stated: "These encouraging results continue to enhance the Livengood project and the opportunities continue to grow as our Company evaluates multiple development options. Our development team is committed to optimizing this large and expanding gold deposit into the best project possible for the Company and advancing the project through to development and production as rapidly as possible."

Expansion and Exploration Potential

Early step-out results from MK-RC-0172 (74 m @ 1.0 g/t gold, previously reported, hole lost in mineralization) in the Olive Zone to the southwest of the Core Zone are encouraging, with MK-RC-0380 encountering 21 metres of 1.73 g/t gold and 44 metres of 1.3 g/t gold and MK-RC-0391 (assays pending) intersecting similar alteration in the same stratigraphic interval (see Figure 1 for drill hole locations and Table 1 for intercepts. To view Figure 1, please click on the following link: http://media3.marketwire.com/docs/ith817m.pdf). Significant additional drilling will focus on this emerging expansion of the Money Knob deposit.

Table 1: Significant Drill Intercepts, Money Knob Deposit*
(*Intercepts are calculated using a 0.25g/t gold cutoff and a maximum of 3 metres of internal waste)

Drill Hole # From (metres) To (metres) Length (metres) Gold (g/t) Area
MK-RC-0373 80.77 89.92 9.15 1.55 Sunshine (infill)
103.63 155.45 51.82 0.71
330.71 347.47 16.76 0.62
353.57 402.34 48.77 1.92

MK-RC-0374 85.34 91.44 6.1 0.91 Core (infill)
135.64 152.4 16.76 0.72
164.59 182.88 18.29 0.72
225.55 236.22 10.67 0.98
243.84 265.18 21.34 0.83
370.33 393.19 22.86 0.5

MK-RC-0375 53.34 62.48 9.14 0.71 Core (infill)
181.36 225.55 44.19 0.76
254.51 262.13 7.62 0.66
313.94 316.99 3.05 6.74
333.76 338.33 4.57 1.16
384.05 390.14 6.09 1.02
394.72 397.76 3.04 2.13

MK-RC-0376 51.82 56.39 4.57 2.45 Sunshine (Infill)
62.48 71.63 9.15 0.76
83.82 92.96 9.14 0.93
97.54 141.73 44.19 0.76
303.28 341.38 38.1 0.9
362.71 377.95 15.24 1.17

MK-RC-0377 123.44 132.59 9.15 0.49 Tower

MK-RC-0378 10.67 32 21.33 0.96 Sunshine (Infill)
38.1 79.25 41.15 1.27
83.82 106.68 22.86 0.56
111.25 330.71 219.46 0.94
includes 45.72 54.86 9.14 3.65
includes 228.6 251.46 22.86 1.66
338.33 358.14 19.81 0.5

MK-RC-0379 28.96 36.58 7.62 1.12 Tower


MK-RC-0380 205.74 207.26 1.52 4.25 Olive
216.41 237.74 21.33 1.73
includes 224.03 230.12 6.09 4.46
245.36 271.27 25.91 0.57
284.99 329.18 44.19 1.3
338.33 353.57 15.24 0.66

MK-RC-0381 211.84 227.08 15.24 0.69 Tower

MK-RC-0382 24.38 56.39 32.01 0.5 Sunshine (Infill)
59.44 118.87 59.43 0.59
120.4 181.36 60.96 2.65
includes 135.64 149.35 13.71 9.15
224.03 236.22 12.19 0.58
259.08 280.42 21.34 0.9
288.04 300.23 12.19 0.69

MK-RC-0383 350.52 359.66 9.14 0.51 Olive

MK-RC-0384 0 3.05 3.05 1.79 Lillian

MK-RC-0385 0 10.67 10.67 0.92 Sunshine (Infill)
54.86 73.15 18.29 0.61
118.87 176.78 57.91 0.54
184.4 240.79 56.39 0.73
246.89 269.75 22.86 0.74
275.84 353.57 77.73 0.64

MK-RC-0386 79.25 109.73 30.48 0.54 Sunshine (Infill)
114.3 158.5 44.2 0.84
185.93 245.36 59.43 0.65
266.7 269.75 3.05 2.76
283.46 310.9 27.44 0.93

MK-RC-0387 353.57 362.71 9.14 0.69 Olive

MK-RC-0388 No significant intercepts, lost hole Lillian

MK-RC-0389 No significant intercepts, lost hole Lillian

MK-RC-0390 0 60.96 60.96 0.48 Sunshine (Infill)
99.06 114.3 15.24 0.5
211.84 233.17 21.33 0.54

MK-10-52 150.57 154.98 4.41 2.64 Core (infill)
179.38 190.33 10.95 0.53
213.97 217.85 3.88 2.25

MK-10-53 76.92 82.13 5.21 6.75 Core (infill)
105.87 123.48 17.61 0.73
142.08 176.91 34.83 1.29
249.39 258.02 8.63 0.66
304.38 311.8 7.42 0.94

MK-10-54 174.04 176.48 2.44 6.91 Money Knob

MK-10-55 134.46 170.78 36.32 1.53 Core (infill)
210.25 237.06 26.81 0.69
284.42 292.53 8.11 0.86
324.53 334.67 10.14 0.64

Infill Drilling Program

The 2010 infill drilling program is a key component in the Livengood pre-feasibility study, and has three main goals: (1) to convert the bulk of the current estimated resource in the mine plan from the indicated and inferred categories to the measured and indicated categories, respectively, (2) to better define the higher grade areas of the deposit, and (3) to extend the deposit at depth, because many of the existing drill holes have ended in mineralization. This work is being completed with a combination of core and RC drilling (two core rigs and two RC drills). Recent drilling in the Sunshine Zone is significantly upgrading the core of the zone: MK-RC-0378 (219 m @ 0.94 g/t gold) and MK-RC-0382 (61 m @ 2.65 g/t gold) are two of the better holes drilled in the Sunshine Zone to date.
 
Aug 19, 2010 09:15 ET
International Tower Hill Adds Depth to its Livengood Project Development and Marketing Team

VANCOUVER, BRITISH COLUMBIA--(Marketwire - Aug. 19, 2010) - International Tower Hill Mines Ltd. ("ITH" or the "Company") - (TSX:ITH)(NYSE Amex:THM)(FRANKFURT:IW9) is pleased to announce the addition of two key members of the Livengood project development team. Keith Malone has accepted the position of Manager of Technical Services and Richard Moses has agreed to come on as Livengood Site Manager. Both Keith and Richard will report to Karl Hanneman, the Livengood Project General Manager. In addition, Shirley Zhou has become a consultant to ITH and will be the Manager of Corporate Communications.

Mr. Malone has 28 years of experience in mine management, most recently as Mine Superintendent with Sumitomo group at the Pogo mine, Alaska's second largest gold mine located 150 kilometres southeast of Fairbanks, Alaska. Mr. Malone has been with the Pogo project for the past 6 years during its planning, construction and operation and has extensive experience in the mining and processing side of project development. Prior to his involvement with the Pogo project, Mr. Malone worked for 5 years as Mill Superintendent for Teck Resources at the Red Dog mine in western Alaska.

Mr. Moses has 36 years of exploration and project management experience, most recently as the project manager for Altynalmas Gold on the Bakyrchik deposit in Kazakhstan. Prior to this, Richard worked in Alaska as project manager on various other projects including Pebble and Donlin Creek. Mr. Moses has extensive experience managing large drilling and development programs, particularly in Alaska.

Ms. Zhou has worked as a corporate communications professional for the past 7 years, and has combined experience in investor/public relations, corporate communications, strategic marketing, client services, sales and journalism. Most recently, she held the role of Corporate Communications Manager for Silvercorp Metals Inc. for two years. Prior to that, she has held the position of Corporate Communications and Investor Relations for several publicly traded resource companies focused on silver, uranium, base metals and potash exploration since 2005.

Jeff Pontius, President and CEO for ITH, stated, "The addition of Mr. Moses and Mr. Malone has added considerable depth and competence to the ITH team as we take the Livengood project forward toward development and production. Both Richard and Keith will fill key management roles as we optimize and maximize the value of our world class gold project. The addition of Ms. Zhou to our Corporate Communications team will greatly enhance our ability to communicate the existing and growing potential of our company as we make the transition toward a gold producer."

Grant of Incentive Stock Options

The Company also announces that, pursuant to its 2006 Incentive Stock Option Plan, it has granted its employees, directors and contractors incentive stock options to purchase 1,495,000 common shares in the capital stock of the Company. The options are exercisable on or before August 20, 2012 at a price of CAD 6.57 per share.

About International Tower Hill Mines Ltd.

International Tower Hill Mines Ltd. is a resource exploration company, focused in Alaska and Nevada, which controls a number of exploration projects representing a spectrum of early stage to the advanced multimillion ounce gold discovery at Livengood. ITH is committed to building shareholder value through new discoveries while maintaining a majority interest in its key holdings, thereby giving its shareholders the maximum value for their investment.

On behalf of International Tower Hill Mines Ltd.

Jeffrey A. Pontius, President and Chief Executive Officer
 
2010-08-19 12:04 ET - News Release

Also News Release (C-ITH) International Tower Hill Mines Ltd

Mr. Bill Wishart of First Star reports

DEFINITIVE AGREEMENT SIGNED BETWEEN FIRST STAR RESOURCES INC. AND INTERNATIONAL TOWER HILL MINES INC.

First Star Resources Inc.'s letters of intent that it has entered into with International Tower Hill Mines Ltd. and its subsidiary, Raven Gold Alaska Inc., previously reported in Stockwatch on March 25, 2010, and amended on July 21 and Aug. 9, 2010 (also reported in Stockwatch), have been accepted and agreed to by all parties. The definitive agreements for the exploration and development of each of the LMS gold prospect and the WP gold prospect, both located in the Goodpaster mining district in Alaska, give First Star the right to earn a 100-per-cent interest in each of the projects. "We are very pleased to have this agreement in place with International Tower Hill Mines and Raven Gold, as it further solidifies our partnership and commitment in exploring these great properties. We are very anxious and excited to begin drilling shortly and sharing results with our eagerly awaiting shareholders," said Bill Wishart, president and chief executive officer First Star Resources.

We seek Safe Harbor.
 
Int'l Tower Hill receives Corvus Gold spin-out approval
Ticker Symbol: C:ITH
Int'l Tower Hill receives Corvus Gold spin-out approval
International Tower Hill Mines Ltd (C:ITH)
Shares Issued 67,222,734
Last Close 8/20/2010 $6.56
Monday August 23 2010 - News Release

Mr. Jeffrey Pontius reports

INTERNATIONAL TOWER HILL RECEIVES FINAL ORDER APPROVING CORVUS GOLD INC. SPIN-OUT ARRANGEMENT

On Friday, Aug. 20, 2010, the Supreme Court of British Columbia granted the final order approving the plan of arrangement under the Business Corporations Act (B.C.) under which International Tower Hill Mines Ltd. will spin out its Alaska and Nevada projects (other than the Livengood project) to Corvus Gold Inc. The effective time for the implementation of the plan of arrangement is expected to be 12:01 a.m. PT on Thursday, Aug. 26, 2010.

The Company will be mailing Letters of Transmittal to all registered shareholders today. If your current ITH common shares ("Existing ITH Shares" - CUSIP 46051L104) are held through your broker, your broker, or the depositary with which your broker holds such shares, will be responsible for dealing with the exchange of Existing ITH Shares for new ITH common shares ("New ITH Shares") and the distribution of Corvus common shares ("Corvus Shares") on your behalf.

To receive certificates representing New ITH Shares and Corvus Shares, registered shareholders must surrender their certificates for Existing ITH Shares, together with a duly completed Letter of Transmittal, to Computershare Investor Services Inc. ("Depositary") at the address shown on the Letter of Transmittal. Upon surrender to the Depositary for cancellation of a certificate which, immediately prior to the Effective Time, represented Existing ITH Shares, together with a properly executed Letter of Transmittal, the holder of such surrendered certificate will be entitled to receive, and the Depositary will deliver to such holder, certificates representing that number (rounded down to the nearest whole number) of New ITH Shares and Corvus Shares that such holder has the right to receive pursuant to the Plan of Arrangement and the surrendered certificate will be cancelled.

In the event of a transfer of ownership of Existing ITH Shares that is not registered in the transfer records of the Company, certificates representing the proper number of New ITH Shares and Corvus Shares may be issued to the transferee if the certificate representing such Existing ITH Shares is presented to the Depositary, accompanied by all documents required to evidence and effect such transfer. Until surrendered, each certificate which, immediately prior to the Effective Time, represented Existing ITH Shares will be deemed, at any time after the Effective Time, to represent only the right to receive upon such surrender the certificates representing New ITH Shares and Corvus Shares that the holder thereof has the right to receive in respect of such certificate pursuant to the Plan of Arrangement.

The Company anticipates that, within a few days after August 26, 2010, and subject to compliance with all of the TSX requirements, including receipt by the TSX of all required documentation, the Corvus Shares will commence trading on the TSX. The New ITH Shares will commence trading at the same time. Advance notice of the commencement of such trading will be provided by press release.

About Corvus Gold Inc. (Post Effective Time)

Corvus Gold Inc. is a resource exploration company, focused in Alaska and Nevada, which controls a number of exploration projects representing a spectrum of early stage to the more advanced North Bullfrog Project in Nevada. Corvus is committed to building shareholder value through new discoveries while maintaining a majority interest in its key holdings, thereby giving its shareholders the maximum value for their investment.

© 2010 Canjex Publishing Ltd.
 
International Tower Hill Clarifies Trading of ITH and Corvus Shares from August 26-27, 2010

VANCOUVER, BRITISH COLUMBIA, Aug 25, 2010 (MARKETWIRE via COMTEX News Network) --
International Tower Hill Mines Ltd. ("ITH" or the "Company") - (TSX: ITH)(NYSE Amex: THM)(FRANKFURT: IW9) wishes to clarify trading of the common shares of both ITH and Corvus Gold Inc. ("Corvus") for the period of August 26-27, 2010.

For Shareholders trading on the TSX

It is anticipated that ITH and Corvus will not trade on the TSX as two separate companies until August 30, 2010. In order to receive Corvus shares, an investor must execute a trade to purchase ITH common shares on the TSX before Corvus and ITH trade as separate companies (currently expected to be August 30, 2010). Specifically, ITH common shares will trade on the TSX as existing ITH common shares ("Existing ITH Shares" - CUSIP 46051L104) with an entitlement to Corvus shares from the opening of trading on August 26, 2010 through to at least the closing of trading on August 27, 2010, despite the fact that the effective time for the implementation of the Plan of Arrangement between ITH and Corvus will be 12:01 am (Vancouver time) on Thursday, August 26, 2010 ("Effective Time"). During this period of time, the price of Existing ITH Shares on the TSX will likely reflect the price of the existing Company as if the Plan of Arrangement was not yet effective. If you sell your Existing ITH Shares on the TSX in this period you will be selling your entitlement to Corvus shares under the Plan of Arrangement. After the time that ITH and Corvus trade as two separate companies (currently anticipated to be the opening on August 30, 2010, ITH common shares will trade on the TSX as new ITH common shares ("New ITH Shares") and will no longer represent a right to receive Corvus shares under the Plan of Arrangement.

For Shareholders trading on the NYSE Amex

ITH will trade on the NYSE Amex as a separate "Post Effective Time" company beginning at the opening on August 26, 2010. In order to receive Corvus shares, an investor must execute a trade to purchase ITH common shares on the NYSE Amex before August 26, 2010. Specifically, ITH common shares will trade on the NYSE Amex as Existing ITH Shares with an entitlement to Corvus shares until the close of trading on August 25, 2010. After the Effective Time, beginning with the opening of trading on August 26, 2010, ITH common shares will trade on the NYSE Amex as New ITH Shares and will no longer represent a right to Corvus shares under the Plan of Arrangement.

Note that this means the trading on the TSX and the NYSE Amex will not be in parity from August 26, 2010 until the time that ITH and Corvus trade as two separate companies on the TSX (currently anticipated to be the opening on August 30, 2010).

Please refer to the Company's press release dated August 23, 2010 for more detailed information on the Plan of Arrangement, available on SEDAR at www.sedar.com.

About Corvus Gold Inc. (Post Effective Time)

Corvus Gold Inc. is a resource exploration company, focused in Alaska and Nevada, which controls a number of exploration projects representing a spectrum of early stage to the more advanced North Bullfrog Project in Nevada. Corvus is committed to building shareholder value through new discoveries while maintaining a majority interest in its key holdings, thereby giving its shareholders the maximum value for their investment.

About International Tower Hill Mines Ltd. (Post Effective Time)

International Tower Hill Mines Ltd. is a resource exploration company, focused in Alaska, which controls the advanced multimillion ounce gold discovery at Livengood. ITH is committed to building shareholder value through aggressively proceeding with the ongoing development of the Livengood project.

On behalf of INTERNATIONAL TOWER HILL MINES LTD.

Jeffrey A. Pontius, President and Chief Executive Officer
 
International Tower Hill Mines Ltd. (ITH) has the following new filing(s) recently:

MAI, QUENTIN
SEDI Insider Relationship:
5 - Senior Officer of Issuer

Acquired 50,000 Options (Indirect Ownership: Quatloo Investment Management Inc.) at a price of $6.570 through granting of options on August 19th, 2010 (Holdings Change* of >= 100%)
 
International Tower Hill Mines Ltd.: Corvus Gold Inc. Spinout Effective; Corvus Shares to Trade on TSX on August 30, 2010

VANCOUVER, BRITISH COLUMBIA, Aug 26, 2010 (MARKETWIRE via COMTEX News Network) --
International Tower Hill Mines Ltd. ("ITH" or the "Company") (TSX: ITH)(NYSE Amex: THM)(FRANKFURT: IW9) announces that the previously announced Plan of Arrangement, under which the Company will spin-out its Alaska and Nevada projects (other than the Livengood Project) to Corvus Gold Inc. ("Corvus"), became effective at 12:01 a.m. today, August 26, 2010.

The "new" common shares of the Company (CUSIP #46050R102) and the common shares of Corvus (CUSIP #221013105) will each commence trading on the Toronto Stock Exchange, effective at the opening, on Monday August 30, 2010. The symbol for "new" ITH common shares is "ITH" and the symbol for the common shares of Corvus is "KOR". Concurrently, the "old" common shares of ITH (CUSIP #46051L104) will be delisted.

The "new" common shares of ITH (CUSIP #46050R102) commenced trading on the NYSE Amex effective at the opening today, August 26, 2010.

Please refer to the Company's press release dated August 23, 2010 and Information Circular dated July 9, 2010 for more detailed information on the Plan of Arrangement, both of which are available on SEDAR at www.sedar.com.

About Corvus Gold Inc.

Corvus Gold Inc. is a resource exploration company, focused in Alaska and Nevada, which controls a number of exploration projects representing a spectrum of early stage to the more advanced North Bullfrog Project in Nevada. Corvus is committed to building shareholder value through new discoveries while maintaining a majority interest in its key holdings, thereby giving its shareholders the maximum value for their investment.

About International Tower Hill Mines Ltd.

International Tower Hill Mines Ltd. is a resource exploration company, focused in Alaska, which controls the advanced multimillion ounce gold discovery at Livengood. ITH is committed to building shareholder value through aggressively proceeding with the ongoing development of the Livengood project.

On behalf of INTERNATIONAL TOWER HILL MINES LTD.

Jeffrey A. Pontius, President and Chief Executive Officer

This press release contains forward-looking statements within the meaning of Section 27A of the Securities Act and Section 27E of the Exchange Act. All statements, other than statements of historical fact, included herein are forward-looking statements. Although the Company believes that such statements are reasonable, it can give no assurance that such expectations will prove to be correct. Forward-looking statements are typically identified by words such as: believe, expect, anticipate, intend, estimate, postulate and similar expressions, or are those, which, by their nature, refer to future events. The Company cautions investors that any forward-looking statements by the Company are not guarantees of future results or performance, and that actual results may differ materially from those in forward looking statements as a result of various factors as disclosed in the Company's annual information form filed with Canadian securities commission and its annual report on Form 40-F filed with the United States Securities and Exchange Commission, and other information released by the Company and filed with the appropriate regulatory agencies. All of the Company's Canadian public disclosure filings may be accessed via www.sedar.com and its United States public disclosure filings may be accessed via www.sec.gov, and readers are urged to review these materials, including the technical reports filed with respect to the Company's mineral properties.

NR10-30

Contacts:International Tower Hill Mines Ltd.Quentin MaiVice-President - Corporate Communications1-888-770-7488 (toll free) or (604) 683-6332(604) 408-7499 (FAX)qmai@internationaltowerhill.comwww.internationaltowerhill.com
SOURCE: International Tower Hill Mines Ltd.

mailto:qmai@internationaltowerhill.com http://www.internationaltowerhill.com

Copyright 2010 Marketwire, Inc., All rights reserved.
 
Jeffrey A. Pontius has the following new filing(s) recently:

INTERNATIONAL TOWER HILL MINES LTD. (ITH)
Title: President & CEO
SEDI Insider Relationship: 5 - Senior Officer of Issuer

Acquired 300,000 Options (Direct Ownership) at a price of $6.570 through granting of options on August 19th, 2010 (Holdings Change of 52.6%)

Insider transaction information sourced from SEDI®
 
Mining News: Tower Hill unlikely to clone Fort Knox

Junior aims to investigate larger operation, heap leach-only scenario as it advances multimillion-ounce Livengood gold deposit

By Shane Lasley

Mining News

Having completed a preliminary economic assessment for the Livengood project in early August, International Tower Hill Mines Ltd. has shifted its focus toward bringing the multimillion-ounce gold property into production.

“Our operational team is making excellent progress in advancing the project down the development and permitting path, a process which we will continue to accelerate,” Tower Hill President and CEO Jeff Pontius told Mining News Aug. 17.

The PEA envisions a heap leach pad and mill similar in scale to those at Kinross Gold Corp.’s Fort Knox Mine about 60 miles, or 100 kilometers, southeast. Processing 81,000 metric tons of ore per day Livengood would produce an average of 504,000 ounces of gold annually over a 21-year mine life.

Though the PEA demonstrates that a clone of the Fort Knox mill and heap leach operation at Livengood would be economic, Tower Hill is unlikely to pursue that development scenario. A final report on the PEA, due to be released by mid-September, will outline two alternatives more apt to resemble the project’s final design.

“In the final report, there will be a couple of alternatives that will be looked at in some detail – one of going initially with a heap leach for six or seven years so we can pay our way to build the mill, (and) the other of doubling the capacity of the mill so we can mine it out in a more reasonable time-period,” Pontius said.

Fort Knox clone
According to the PEA, building a Fort Knox-sized mine at Livengood would cost around US$1.385 billion, with an additional US$450 million in life-of-mine sustaining capital costs. The figures used in the assessment include a 25 percent contingency on capital costs, a number that should decrease as the mine plan becomes more certain.

“The base-case we put in there was basically cloning the current Fort Knox operation and sticking it at Livengood. One of the drawbacks that we saw is that Livengood is considerably bigger than Fort Knox, and it had such a long mine-life, it didn’t produce as good financial results as it could have if (we) increased mill production to compress that 21-year life,” Pontius explained.

Though much can be done to improve the profitability of the project, the PEA did demonstrate positive economics. At US$950 per ounce gold, the conceptual project has a pre-tax net present value (at a 5 percent discount) of US$813 million and an internal rate of return of 15.4 percent. The study also shows the deposit has a considerable leverage to gold prices, with a pre-tax NPV (5 percent) of US$2.3 billion and an IRR of 32.5 percent at US$1,200 per ounce gold.

“The positive results from this economic assessment will form the conceptual foundation of the Livengood project design, which is projected to consist of a large open-pit mine supplying ore to both a large mill using gravity and flotation concentration and a heap leach pad with associated gold recovery circuit,” said Tower Hill Chief Operating Officer Carl Brechtel. “The authors of this most recent PEA will continue on as key external members of the company’s owner team, providing continuity in the transition to the prefeasibility study. The prefeasibility study will address a number of optimization and enhancement opportunities to continue to improve and grow the project.”

Two alternatives
The two optimization and enhancement options under consideration are increasing the mine rate and beginning with a heap leach-only operation for the first few years.

With capital costs at about half that of constructing a combined mill-heap leach operation, an initial heap leach-only option is an attractive alternative if Tower Hill puts Livengood into operation on its own.

“That is a real option for us because bringing the heap on would lower the initial (capital expenditure), and it allows ITH to look at a way financially it can take the project forward,” Pontius told Mining News.

“If ITH is building this project, we are going to want to run the heap gangbusters for a while to actually get some good cash,” he added.

The Money Knob deposit at Livengood contains some 300 million metric tons of heap-leachable oxidized mineralization, a number the company expects to increase as drilling results increase the deposit size to the west.

“We have expanded the two best heap leach units, which are the Cambrian and Upper Sedimentary, to the point where they could support a very large mine for about seven years at a throughput of 100,000 tons a day,” Pontius explained.

With cash coming in the company could later opt to build a mill to mine the deeper unoxidized ore.

The other option under consideration is ratcheting up the size of the operation.

“It’s a very large deposit with over 10 million recoverable ounces – half a million ounces a year of production, which has an opportunity to increase as we enlarge the operation to take advantage of economies of scale,” Pontius said.

Livengood is particularly suited for a larger-scale operation. Not only is it an enormous ore-body, it has a low ore-to-strip ratio of 1-to-1.07 and large mineralized units.

“The strip ratio is approximately 1-to-1 in the deposit and affords us a great opportunity to scale this operation up and compress the mine-life, which should improve the overall economics of the project,” Pontius said.

A larger operation comes with a larger price tag. If the scaled-up option is pursued, it is likely that a major company would join Tower Hill to build the mine.

“Of course we will be continuing on (with) putting both scenarios out there; one where we bring a heap leach on early and get it going and start to make cash out of the project so we can finance the mill construction, and the other one is to do it all at once – bring the mill, the heap leach push it forward on a very large-scale basis like a big company would do, that isn’t capital constrained,” the Tower Hill CEO explained.

Prefeasibility under way
Working out the pros and cons of the various scenarios will be part of the prefeasibility study currently underway.

“We have good infrastructure, we are in a very favorable jurisdiction, we have strong local support for this project, and we are moving it forward very quickly into the prefeasibility phase,” Pontius said.

As engineers hammer out the mine plans, scientists are on the ground collecting the hydrological, environmental and other data needed to permit the project.

With the addition of personnel conducting the baseline studies, Pontius said the population of the Livengood camp swelled to more than 80 people this summer.

In addition to the field programs, Tower Hill will soon award a contract for more in-depth phase-2 metallurgical work.

Denser, deeper drilling
The infill portion of this summer’s 45,000-meter drill campaign is a key component of the Livengood prefeasibility study. The primary goals of the two core rigs and one reverse circulation drill engaged in the infill program is to convert the bulk of the resources included in the mine-plan to measured and indicated categories, better define the higher-grade areas of the deposit and extend the mineralization at depth.

Tower Hill believes this summer’s infill drill campaign will provide enough density to upgrade the bulk of the 10.9-million-ounce indicated and 2.4-million-ounce inferred gold resource. The grades are also holding up to the density drilling and may increase slightly when a new resource is calculated.

Many of the holes drilled into Money Knob have bottomed out in mineralization, indicating that the deposit has room to grow at depth. Two holes drilled into the Sunshine zone this summer highlight this potential. At a depth of 353 meters, hole MK- RC-0373 cut 49 meters grading 1.9 of gold per metric ton. From 363 meters hole MK-RC-0376 drilled 15 meters averaging 1.2 g/t gold.

Seeking gold-poor regions of the property suitable for building the heap leach pad, mill and other facilities is another facet of the drill program that will provide information the engineers need as they complete the feasibility study.

“Right now we have half a dozen or so facility alternatives on the property package, and we are going to need to evaluate those, because some of them have some very interesting gold anomalies associated with them,” Pontius explained.

Expansion continues
The junior is also continuing to expand the footprint of Money Knob. Two reverse circulation drills evaluating resource expansion and district-scale targets at Livengood have returned encouraging results on opposite ends of deposit.

“We are stepping out in a couple of new areas; one down the Lillian Gulch area and the other one (Olive Zone)is to the south of the Core Zone as we come off the side of the hill there – we have had luck in both those spots,” Pontius explained.

Hole RC-0355, drilled in Lillian Gulch about 400 meters north and west of known mineralization, cut 7.6 meters grading 3.3 grams per metric ton gold. RC-0362, drilled 150 meters east of hole 355 intersected 6.1 meters grading 2.9 g/t. These results along with anomalous gold in soils have prompted the explorer to continue its investigation of this expansion area. RC-0392, drilled about 600 meters north of hole 355, intersected strongly altered favorable host rocks. Assay results are still pending from this hole drilled in the northern portion of the Lillian zone.

Olive, an expansion area southeast of the Core zone, is also showing promise. Hole MK-RC-0380 cut 21.33 meters averaging 1.73 g/t gold and included 6.09 meters grading 4.46 g/t gold. Assays are pending on several holes drilled in this promising new area.

An aggressive district-wide surface exploration campaign to define new deposits similar to Money Knob along trend has turned up some promising targets for a drill campaign expected to begin this fall.

“We have got a big regional soil program going on within the large land-block we’ve got and we have defined a lot of targets out there. Hopefully in mid-September we’ll have got some helicopter-supported reconnaissance drilling on some of those targets to see if we’ve got other deposits in the trend,” Pontius added.
 
ITH!!



Stockhouse didn't post properly the area I highlighted it's in this paragraph.

International Tower Hill Mines Ltd. ("ITH" or the "Company") - is pleased to announce the results from the latest 17 drill holes completed in its 50,000-metre Summer 2010 Livengood Exploration Program (Table 2). Highlighted in these latest holes is not only the continued confirmation and expansion of the deposit but the expansion of a shallow, high-grade, northwest trending zone within the Core Zone (MK-RC-405: 6.1m @ 18.2 g/t gold). This consistent trend of +6 g/t mineralization, which extends for nearly a half a kilometre within the large lower grade deposit, is emerging as one of the key early mining targets for the deposit. In addition the newly discovered Olive Zone continues to expand to the north (MK-RC-391: 45.7m @ 1.1 g/t gold) and south (MK-RC 396: 13.7m @ 2.1 g/t gold).


OgAAAA5SFA0pKzwQ9DnthNJ5sAHiSpX5tG9MNqocmBLBCZohfDMlDiAxyEN8NLBRDBPxgcLr6qfReXmUMxlOT82wrvsAm1T1UFsVFH_wdYT5-2rfCiJOiKFjKfzl.jpg


OgAAAH9dXYKQkWUHTUODnCtWASlYht01DP0ZzwR_Z94l7fDeuxhyG20TdEzSHOsKoFr4rCD5Nqy9US2p38jwjWbq8FwAm1T1UFe9BXRKV2AFLMMrAxoDQSocpbYI.jpg


OgAAAMmQXyH_G5Q5wmhzFShVKoAL54xzrV1wt5jBnJPLX7KpZI-8goRP-BqhZOq_S3513vyyMqDSCOrOvbYimg7Q4BcAm1T1UD5y4PHdAQPbrJvujfYh-tjMS1SZ.jpg


In voller Grösse! Man beachte die Bahnverbindung!!
 
14.09.2010 00:04

International Tower Hill Mines Ltd.: Project Enhancement Options for its Preliminary Economic Assessment Study for the Livengood Gold Project, Alaska

VANCOUVER, BRITISH COLUMBIA -- (Marketwire) -- 09/13/10 -- International Tower Hill Mines Ltd. (TSX: ITH)(NYSE Amex: THM)(FRANKFURT: IW9) -

Low Capex Accelerated Heap Option: NPV(5%) $579M, IRR 26.9%, Producing 513,000 ounces of gold/year

Upscale Milling-Heap Option: NPV(5%) $1.11B, IRR 18.5%, Producing 833,000 ounces of gold/year

International Tower Hill Mines Ltd. ("ITH" or the "Company") (TSX: ITH)(NYSE Amex: THM)(FRANKFURT: IW9) is pleased to announce results from the next phase of its Project Enhancement Options within its independently prepared Preliminary Economic Assessment (PEA) for the Livengood Gold Project, Alaska. Management anticipates continuing to refine and improve project economics as additional information becomes available. The results from this phase of the Company's PEA report highlight two important alternatives under consideration for the potential development of the Livengood gold deposit. All references to monies in this news release are to US dollars unless otherwise indicated.

The first alternative outlines an initial low capex, accelerated heap leach only option which could provide cash flow to support the development of a large mill phase for the project (Tables 1&2). The second alternative looks at expanding the projected milling circuit which benefits the project through economies of scale, increased production and compressed mine life (Tables 3&4). These alternatives offer significant enhancement to the base case plan presented in ITH's August 3, 2010 news release and point to the significant potential that the large Livengood deposit has for further optimization.

The heap leach only option is emerging as a highly attractive initial stage for ITH because it is a simpler project from the permitting, process, construction and operational standpoints, all of which can be accelerated. This alternative also has much lower capex and operating costs, which produces a compelling internal rate of return, NPV and annual gold production. The large mill-heap option reflects overall project value and has significant leverage to gold price.

Jeffrey Pontius, President and CEO, stated, "The option analysis has highlighted not only a strategic path forward for ITH's development of the Livengood project but also the value potential of this new world class gold discovery. As the Company focuses on optimizing the development of Livengood with the reduced capex, accelerated plan for heap leaching, we will also be continuing to examine other options, such as a simple, heap compatible mill, to address the deposit's emerging contiguous higher grade zones. The analysis of this and other options are currently in full swing as the project begins the optimization phase."


Table 1
Livengood Project - Heap Leach Only Option - PEA Summary
(all values in 2010 USD based on an $775 pit shell, mining recoverable
in-pit resources above 0.3 g/t gold cut off)

---------------------------------------------------------------------------
251Mt @ 0.62 g/t gold for 5.03M
contained ounces gold, 3.54M recoverable
In-pit resource - Indicated ounces gold
---------------------------------------------------------------------------
9 Mt @ 0.54 g/t gold for 0.15M contained
ounces gold, 0.11M recoverable ounces
In-pit resource - Inferred gold
---------------------------------------------------------------------------
NPV(5%) and IRR at USD 950 per Oz USD 579M; 26.9%
---------------------------------------------------------------------------
1 to 1.1 (mined mineral resource to
Over all strip ratio of: waste)
---------------------------------------------------------------------------
Average Annual gold production: 513,000 ounces over a 7.1 year mine life
---------------------------------------------------------------------------
Average gold recovery: 71%
---------------------------------------------------------------------------
100,000 mined mineral resource tonnes
Average LOM Mining rate: per day, 210,000 total tonnes per day
---------------------------------------------------------------------------
Mining cost per/tonne: $1.45
---------------------------------------------------------------------------
Heap Leach Processing cost/tonne $3.11
---------------------------------------------------------------------------
G&A cost per processed tonne: $0.81
---------------------------------------------------------------------------
Operating Cost per ounce: $486
---------------------------------------------------------------------------
Initial capital cost(i): $ 638 M
---------------------------------------------------------------------------
Life of mine sustaining capital
costs: $154 M
---------------------------------------------------------------------------
Capital Contingency: 20%
---------------------------------------------------------------------------
(i) excludes working capital and initial fills/spare parts inventory

The Company will file the final version of an update of the NI 43-101 technical report which will include the results of this Preliminary Economic Analysis (the "Report") on SEDAR by September 17, 2010, and investors are urged to review the Report in its entirety.


Table 2
Heap Leach Only Option Gold Price Sensitivity Analysis
(all values in constant 2010 US$)

Gold Price NPV(5%)($M) NPV(7.5%)($M) IRR (%)
---------------------------------------------------------------------------
$950 $579 $456 26.9%
---------------------------------------------------------------------------
$1,100 $988 $813 40.0%
---------------------------------------------------------------------------
$1,200 $1,260 $1,051 47.4%
---------------------------------------------------------------------------
$1,500 $2,077 $1,764 68.4%
---------------------------------------------------------------------------


Table 3
Livengood Project - Large Mill - Heap Leach PEA Summary
(all values in 2010 USD based on an $850 pit shell, mining recoverable
in-pit resources above 0.3 g/t gold cut off)

---------------------------------------------------------------------------
600 Mt @ 0.65 g/t gold for 12.6M
contained ounces gold, 9.8M recoverable
In-pit resource - Indicated ounces gold
---------------------------------------------------------------------------
48 Mt @ 0.64 g/t gold for 1.0M contained
ounces gold, 0.8M recoverable ounces
In-pit resource - Inferred gold
---------------------------------------------------------------------------
NPV(5%) and IRR at USD 950 per Oz USD 1.11B; 18.5%
---------------------------------------------------------------------------
1 to 1.07 (mined mineral resource to
Over all strip ratio of: waste)
---------------------------------------------------------------------------
833,000 ounces over a 12.6 year mine
Average Annual gold production: life
---------------------------------------------------------------------------
Average gold recovery: 78% (73% Heap&81% Mill)
---------------------------------------------------------------------------
135,000 mined mineral resource tonnes
Average LOM Mining rate: per day, 280,000 total tonnes per day
---------------------------------------------------------------------------
Mining cost per/tonne: $1.41
---------------------------------------------------------------------------
Mill Processing cost/tonne: $7.46
---------------------------------------------------------------------------
Heap Leach Processing cost/tonne $2.84
---------------------------------------------------------------------------
G&A cost per processed tonne: $0.59
---------------------------------------------------------------------------
Operating Cost per ounce: $534
---------------------------------------------------------------------------
Initial capital cost(i): $ 625 M
---------------------------------------------------------------------------
Mill&Heap expansion capital cost $1,027 M
---------------------------------------------------------------------------
Life of mine sustaining capital
costs: $579 M
---------------------------------------------------------------------------
Capital Contingency: 25%
---------------------------------------------------------------------------
(i) excludes working capital and initial fills/spare parts inventory



Table 4
Large Mill-Heap Option Gold Price Sensitivity Analysis
(all values in constant 2010 US$)

Gold Price NPV(5%)($M) NPV(7.5%)($M) IRR (%)
---------------------------------------------------------------------------
$950 $1,113 $760 18.5%
---------------------------------------------------------------------------
$1,100 $2,147 $1,611 29.3%
---------------------------------------------------------------------------
$1,200 $2,837 $2,178 35.9%
---------------------------------------------------------------------------
$1,500 $4,906 $3,879 54.4%
---------------------------------------------------------------------------

This PEA utilized preliminary estimates of heap leach and mill recovery, assuming a nominal 73% and 81% process recovery, respectively, for the large milling-heap leach option and an average of 71% for the heap leach only option (includes some minor lower recovery sulphide material in the pit design which would have gone to the mill in the combined study). The estimated mill recovery is consistent with the high average recovery (89%) of gold to concentrate demonstrated in the existing metallurgical testing data and the subsequent total gold recovery by CIL treatment in some of the mined mineral resource types. Metallurgical testing will be conducted as part of a Pre-feasibility Study to verify the total gold recovery assumptions and to support design of the required mill and heap leach processes.

Carl Brechtel, Chief Operating Officer, stated, "The very attractive early stage oxide heap leach project provides a strong base for our Company to begin enhancing the operational planning and economics. This work will focus on advancing both production and grade in the plan while looking for the most economically favourable development strategy that can minimize and mitigate the project's environmental impacts. The size and character of the Livengood deposit will enable the Company to look at a variety of project enhancement options as we progress toward a final design."

The Company cautions that this PEA is preliminary in nature, and is based on technical and economic assumptions which will be evaluated in the Pre-feasibility Study. The PEA is based on the Livengood in-situ resource model (June, 2010) which consists of material in both the indicated and inferred classification. Inferred mineral resources are considered too speculative geologically to have technical and economic considerations applied to them. The current basis of project information is not sufficient to convert the in-situ mineral resources to mineral reserves, and mineral resources that are not mineral reserves do not have demonstrated economic viability. Accordingly, there can be no certainty that the results estimated in this PEA will be realized. The PEA results are only intended as an initial, first-pass review of the potential project economics based on preliminary information.

This Livengood PEA utilizes the June 2010 in-situ resource estimate, which includes all assays completed through May, 2010 (434 diamond and reverse circulation holes). The mine production estimate was developed by incremental revenue optimization to produce a series of pit shells defined at varying gold prices between $300 and $1500 per ounce, for the gold recovery and processing cost assumptions. A long term gold price of $950 per gold ounce has been assumed in this PEA, and the pit shells, defined at $775 and $850 per gold ounce, were selected for the analysis to assure a minimum margin on process cost of greater than $100 per gold ounce. The resulting pit design for the combined heap leach and mill option at projected full extraction is shown in Figure 1, and a series of 5 push-backs were chosen within the shell as the basis of a production schedule that would deliver a nominal 135,000 tonnes/day mined mineral resource output. Individual in-situ resource blocks within the pit shell were assigned an economic value based on recovery and contained gold above the 0.3 g/t cut-off grade, and the blocks were assigned to one of the heap leach, mill or waste dump destinations based on the economic value. For blocks assigned to the heap leach or mill destination, the individual block grade-tonnage data developed in the Multiple Indicator Kriging in-situ resource model was used to calculate the mining recoverable tonnage above the 0.3 g/t cut-off grade. The mining recoverable resource was scheduled to the appropriate process circuit (mill or heap leach) and the remaining material below the 0.3 g/t cut-off was scheduled to the waste rock storage facility.

The Livengood mineralization remains open in a number of directions particularly to the west, southeast and at depth. The Company is continuing its resource expansion drilling campaign which is focused on expanding the higher grade Southwest Zone of the deposit, confirming the inferred resource extrapolation at depth, and infilling the drill pattern to increase the drill density in the core of the Sunshine Zone and Main Zone mineralization.

To view the map accompanying this press release please visit the following link: http://media3.marketwire.com/docs/ithmap913.pdf

Cash Flow Model Inputs and Assumptions

Resources - The analysis included both indicated and inferred resources in the mining and economic study. Indicated resources make up more than 90% of the defined in-pit mineral resource tonnage.

Mining Method - A standard open pit drill, blast, load and haul mining plan was used for the study, assuming a 45 degree pit slope. Designs for pit roads and ramps have been developed, and the schedule includes the additional waste tonnage required. The assumed nominal mining rate was 210,000 and 280,000 total tonnes per day for the heap leach only and mill heap leach combination, respectively (365 operating days per year).

Heap Leach Processing Method - A valley fill heap leach design, initially operated at 100,000 tonnes of mined mineral resource a day, was assumed for the PEA heap leach only option. The mined mineral resource to be heap leached would be crushed to 1.2 cm and truck stacked on the pad.

Combined Heap Leach - Mill Processing Method - A valley fill heap leach design, initially operated at 100,000 tonnes of mined mineral resource a day and declining to nominal 89,000 tonnes of mined mineral resource per day for the first 6 years after the mill start-up in year 4, was assumed for the PEA. The mined mineral resource to be heap leached would be crushed to 1.2 cm and truck stacked on the pad. A process plant using SAG milling, gravity and flotation circuits for concentration and CIL recovery of gold was assumed in the PEA. The process plant was assumed to have a nominal throughput of 100,000 tonnes per day, beginning operation in year 4, after 3 years of heap leach processing.

Gold Recovery Model - Process recoveries were estimated for each of 21 different mineralization types (7 rock types, 3 oxidations states) in the deposit based on metallurgical test results published in the June 2010 update of the Livengood technical data. The quantity of mineralization types are then projected into the in-situ resource block model using a 3D geological model of the deposit, and a process recovery factor is calculated for each model block. The calculated process recovery factor is used to determine produced gold ounces for the portion of mine recoverable material above the 0.3 g/t cut-off grade for each block according to its processing destination (heap leach or mill).

Operating and Capital Cost Estimates - Preliminary capital and operating costs were prepared using information available on other Alaskan gold mines, an independent mining and development cost research report commissioned by the Company, all available project technical data and metallurgical/process related test work, as well as project site reviews by the independent consultants and the Qualified Persons authoring the Report. Preliminary site infrastructure alternatives (heap leach, waste dump, tailing storage facilities, and mill) have been evaluated by independent study and an arrangement defined as the basis of capital cost estimates. Capital costs for the combined heap leach - mill option were estimated from a review of recent gold projects developed in the region. Capital costs were developed based on a nominal mining rate of 135,000 tonnes of mined mineral resource per day (nominal total tonnes mined per day of 280,000), processing a total of 650 Mt, and includes sustaining capital and all facilities and equipment needed for all phases of the project over its projected 12.6 year life. Capital costs for the heap leach only option were estimated from a review of recent gold projects developed in the region. Capital costs were developed based on a nominal mining rate of 100,000 tonnes of mined mineral resource per day (nominal total tonnes mined per day of 210,000), processing a total of 259 Mt, and includes sustaining capital and all facilities and equipment needed for all phases of the project over its projected 7.1 year life. All costs are in constant USD from Q3 2010. No escalation was applied in the financial models.

Taxes and Royalties - Taxes and royalty charges were excluded from this preliminary analysis of the project. Net smelter return royalty rates vary from 0-5% across the project and average approximately 2.5%, assuming exercise by the Company of all available royalty buy-out rights.

Revenue - Revenue was determined in the base case financial model assuming a constant, long term gold price of $950 per Au ounce. All sensitivities to gold price assumptions were assessed using a constant price.

June 2010 Resource Update

Reserva International, LLC. produced an updated in-situ mineral resource estimate, the results of which were included in the June 2010 update of the Livengood NI 43-101 (June 2010 Summary Report on the Livengood Project, Tolovana District, Alaska). Summary results at different cut-off grades are listed in Tables 5, 6 and 7. This in-situ resource estimate was used as the basis for the Mill and Heap Leach PEA.


Table 5
June 2010 Livengood Resources (at 0.30 g/t gold cutoff)

---------------------------------------------------------------------------
Gold Cutoff Tonnes Million Ounces
Classification (g/t) (millions) Gold (g/t) Gold
---------------------------------------------------------------------------
Indicated 0.30 789 0.62 15.7
---------------------------------------------------------------------------
Inferred 0.30 229 0.55 4.0
---------------------------------------------------------------------------


Table 6
June 2010 Livengood Resources (at 0.50 g/t gold cutoff)

---------------------------------------------------------------------------
Gold Cutoff Tonnes Million Ounces
Classification (g/t) (millions) Gold (g/t) Gold
---------------------------------------------------------------------------
Indicated 0.50 409 0.83 10.9
---------------------------------------------------------------------------
Inferred 0.50 94 0.79 2.4
---------------------------------------------------------------------------


Table 7
June 2010 Livengood Resources (at 0.70 g/t gold cutoff)

---------------------------------------------------------------------------
Gold Cutoff Tonnes Million Ounces
Classification (g/t) (millions) Gold (g/t) Gold
---------------------------------------------------------------------------
Indicated 0.70 202 1.07 6.9
---------------------------------------------------------------------------
Inferred 0.70 40 1.06 1.4
---------------------------------------------------------------------------

The scale of the Livengood gold system is demonstrated by the size of the estimated resource using a 0.3 g/t gold cutoff (Table 5). This resource forms a coherent body covering a lateral extent of three square kilometres and remains open in several directions.

The resource model for the deposit was developed using Multiple Indicator Kriging techniques. Indicator variogram modeling was done on 10 metre composites. The resource model was constrained by the lithological model developed by the Company. Spatial statistics indicate that the mineralization shows very reasonable continuity within the range of anticipated operational cutoffs. Bulk density was estimated on the basis of individual density measurements made on core samples and reverse circulation drill chips from each stratigraphic unit. In total, 98 measurements were used. Block density was assigned on the basis of the lithological model. The resource model, with blocks 15 x 15 by 10 metres, was estimated using nine indicator thresholds. A change-of-support correction was imposed on the model assuming 5 x 5 x 10 metre selectable mining units. Classification of indicated and inferred was based on estimation variance.

Livengood Project Highlights


-- Drilling at the project continues to expand the deposit in several
directions; at depth, to the west in the Lillian area and to the
southeast in the Sunshine Zone.
-- The Company has begun the Money Knob pre-feasibility study with the
initiation of hydrological studies, surface mine facility location
analysis, phase 2 metallurgical studies, deposit scale geotechnical
studies, condemnation drilling and the continuing collection of
environmental baseline data.
-- Ongoing metallurgical studies continue to focus on column leach testing
for heap leaching process design, and on gravity and flotation
concentration, which has returned initial average recoveries to
concentrate of 89% and offers a significant potential for operational
and capital cost savings. Optimization work is ongoing for these
processing alternatives, as they have potential to make significant
positive impacts on project economics.
-- The geometry of the currently defined shallowly dipping, outcropping
deposit has a low strip ratio amenable to low cost open pit mining which
could support a high production rate and economies of scale. Future
mining studies will continue to evaluate mining and processing
production rates as well as the possible introduction of a smaller mill
into the heap leach only option which recombines mill tails with heap
material for additional extraction during the heap leach process on the
leach pad.
-- The Livengood project has a very favourable logistical location, being
situated 110 road kilometres north of Fairbanks, Alaska along the paved,
all-weather Elliott Highway, the Trans-Alaska Pipeline Corridor, and the
proposed Alaska natural gas pipeline route. The terminus of the Alaska
State power grid lies approximately 80 kilometres to the south.
-- ITH controls 100% of its approximately 145 square kilometre Livengood
land package, which is made up of fee land leased from the Alaska Mental
Health Trust, a number of smaller private mineral leases and 115 Alaska
state mining claims.
-- No major permitting hurdles have been identified to date.

Geological Overview

The Livengood Deposit is hosted in a thrust-interleaved sequence of Proterozoic to Paleozoic sedimentary and volcanic rocks. Mineralization is related to a 90 million year old (Fort Knox age) dike swarm that cuts through the thrust stack. Primary mineralization controls are a combination of favourable lithologies and crosscutting structural zones. In areas distal to the main structural zones, the selective development of disseminated mineralization in favourable host rocks is the main mineralization control. Within the primary structural corridors, all lithologies can be pervasively altered and mineralized. Devonian volcanic rocks and Cretaceous dikes represent the most favourable host lithologies and are pervasively altered and mineralized throughout the deposit. Two dominant structural controls are present: 1) the major shallow south-dipping faults which host dikes and mineralization which are related to dilatant movement on structures of the original fold-thrust architecture during post-thrusting relaxation, and 2) steep NW trending linear zones which focus the higher-grade mineralization which cuts across all lithologic boundaries. The net result is broad flat-lying zones of stratabound mineralization around more vertically continuous, higher grade core zones with a resulting lower strip ratio for the overall deposit and higher grade areas that could be amenable for starter pit production.

The surface gold geochemical anomaly at Livengood covers an area 6 kilometres long by 2 kilometres wide, of which approximately half has been explored by drilling to date. Surface exploration is ongoing as new targets are being developed to the northeast and west of the known deposit.

Qualified Persons and Quality Control/Quality Assurance

Tim Carew, P.Geo., of Reserva International, LLC., a mining geo-scientist, is a Professional Geoscientist in the province of British Columbia (No. 18453) and, as such, has acted as the Qualified Person, as defined in NI 43-101, for the June 2010 resource modeling for the Livengood deposit. Mr. Carew has a B.Sc. degree in Geology, an M.Sc in Mineral Production Management and more than 34 years of relevant geological and mining engineering experience in operating, corporate and consulting environments. Both Mr. Carew and Reserva International, LLC. are independent of the Company under NI 43-101.

Dr. Paul D. Klipfel, Ph.D., AIPG, a consulting economic geologist employed by Mineral Resource Services Inc., has acted as the Qualified Person, as defined in NI 43-101, for the exploration data and supervised the preparation of the technical exploration information on which some of this news release is based. Dr. Klipfel has a PhD in economic geology and more than 28 years of relevant experience as a mineral exploration geologist. He is a Certified Professional Geologist (CPG 10821) by the American Institute of Professional Geologists. Both Dr. Klipfel and Mineral Resource Services Inc. are independent of the Company under NI 43-101.

Mr. William J. Pennstrom, Jr., of Pennstrom Consulting Inc., a consulting metallurgical engineer, is acting as the Qualified Person, as defined in NI 43-101, for the metallurgy and mineral processing programs for the Livengood deposit, and development of the PEA project financial analysis. Mr. Pennstrom has a BS degree in Metallurgical Engineering and a Masters degree in Business Management. He has more than 26 years of relevant experience as a metallurgist, having functioned as an operator, engineer, and process consultant over this time frame. Mr. Pennstrom is also a Qualified Professional (QP) member of the Mining and Metallurgical Society of America. Both Mr. Pennstrom and Pennstrom Consulting Inc. are independent of the Company under NI 43-101.

Mr. Quinton de Klerk, Director of Mining Solutions at Cube Consulting, Perth Australia, is a consulting mining engineer specializing in open pit design, open pit optimization and analysis, mine design, production scheduling, due diligence evaluations and mineral reserves reporting. He is acting as Qualified Person, as defined in NI 43-101, for the open pit optimization and scheduling work for the Livengood Deposit. Mr. de Klerk has over 15 years experience in open pit mining and is a Corporate Member of AusIMM. He holds a Mine Manager's Certificate in South Africa and a National Higher Diploma in Metalliferous Mining. Both Mr. de Klerk and Cube Consulting are independent of the Company under NI 43-101.

Mr. John Bell, Sr. Project Manager at MTB Project Management Professionals, Inc. of Denver, Colorado, is a graduate civil engineer, with an MBA, specializing in project management, cost estimation, project controls, construction management and contract administration. Mr. Bell is acting as Qualified Person, defined in NI 43-101, for capex and opex cost review for the Livengood Project. Mr. Bell has over 46 years experience working in the engineering and construction industry in North and South America, Europe, Australia and Asia. He is a Life Member of the American Society of Civil Engineers, a member of the Association for Advancement of Cost Engineering, a member of the Institution of Engineers, Australia and a Chartered Professional Engineer in Australia (#172814). Both Mr. Bell and MTB Project Management Professionals, Inc. are independent of the Company under NI 43-101.

Jeffrey A. Pontius (CPG 11044), a qualified person as defined by National Instrument 43-101, has supervised the preparation of the scientific and technical information that forms the basis for this news release and has approved the disclosure herein. Mr. Pontius is not independent of ITH, as he is the President and CEO and holds common shares and incentive stock options.

Development work at the Livengood Project is directed by Carl E. Brechtel (Colorado PE 23212, Nevada PE 8744), who is a qualified person as defined by National Instrument 43-101. He is a graduate geological engineer with an MS degree in mining engineering. He is a member of the Society for Mining, Metallurgy and Exploration located in Denver CO, AusIMM (Australia) and SAIMM (South Africa). Mr. Brechtel has supervised the preparation of the technical and economic information that forms the basis for this news release and has approved the disclosure herein. Mr. Brechtel is not independent of ITH, as he is the COO and holds incentive stock options.

The work program at Livengood was designed and is supervised by Chris Puchner, Chief Geologist (CPG 07048), of the Company, who is responsible for all aspects of the work, including the quality control/quality assurance program. On-site personnel at the project photograph the core from each individual borehole prior to preparing the split core. Duplicate reverse circulation drill samples are collected with one split sent for analysis. Representative chips are retained for geological logging. On-site personnel at the project log and track all samples prior to sealing and shipping. All sample shipments are sealed and shipped to ALS Chemex in Fairbanks, Alaska for preparation and then on to ALS Chemex in Reno, Nevada or Vancouver, B.C. for assay. ALS Chemex's quality system complies with the requirements for the International Standards ISO 9001:2000 and ISO 17025:1999. Analytical accuracy and precision are monitored by the analysis of reagent blanks, reference material and replicate samples. Quality control is further assured by the use of international and in-house standards. Finally, representative blind duplicate samples are forwarded to ALS Chemex and an ISO compliant third party laboratory for additional quality control.

About International Tower Hill Mines Ltd.

International Tower Hill Mines Ltd. is a resource exploration company focused on the ongoing development of the advanced, multimillion-ounce gold discovery at Livengood in Alaska. ITH is committed to the aggressive development of the Livengood Project, thereby giving its shareholders the maximum value for their investment.

On behalf of International Tower Hill Mines Ltd.

Jeffrey A. Pontius, President and Chief Executive Officer

Cautionary Note Regarding Forward-Looking Statements

This press release contains forward-looking statements and forward-looking information (collectively, "forward-looking statements") within the meaning of applicable Canadian and US securities legislation. All statements, other than statements of historical fact, included herein including, without limitation, statements regarding the anticipated content, commencement and cost of exploration programs, anticipated exploration program results, the discovery and delineation of mineral deposits/resources/reserves, the potential for the expansion of the estimated resources at Livengood, the potential for any production at the Livengood project, the potential for higher grade mineralization to form the basis for a starter pit component in any production scenario, the potential low strip ratio of the Livengood deposit being amenable for low cost open pit mining that could support a high production rate and economies of scale, the potential for cost savings due to the high gravity concentration component of some of the Livengood mineralization, the completion of a pre-feasibility study at Livengood, the potential for a production decision to be made regarding Livengood, the potential commencement of any development of a mine at Livengood following a production decision, business and financing plans and business trends, are forward-looking statements.

Information concerning mineral resource estimates and the preliminary economic analysis thereof also may be deemed to be forward-looking statements in that it reflects a prediction of the mineralization that would be encountered, and the results of mining it, if a mineral deposit were developed and mined. Although the Company believes that such statements are reasonable, it can give no assurance that such expectations will prove to be correct. Forward-looking statements are typically identified by words such as: believe, expect, anticipate, intend, estimate, postulate and similar expressions, or are those, which, by their nature, refer to future events. The Company cautions investors that any forward-looking statements by the Company are not guarantees of future results or performance, and that actual results may differ materially from those in forward looking statements as a result of various factors, including, but not limited to, variations in the nature, quality and quantity of any mineral deposits that may be located, variations in the market price of any mineral products the Company may produce or plan to produce, the Company's inability to obtain any necessary permits, consents or authorizations required for its activities, the Company's inability to produce minerals from its properties successfully or profitably, to continue its projected growth, to raise the necessary capital or to be fully able to implement its business strategies, and other risks and uncertainties disclosed in the Company's Annual Information Form filed with certain securities commissions in Canada and the Company's annual report on Form 20-F filed with the United States Securities and Exchange Commission (the "SEC"), and other information released by the Company and filed with the appropriate regulatory agencies. All of the Company's Canadian public disclosure filings may be accessed via www.sedar.com and its United States public disclosure filings may be accessed via www.sec.gov, and readers are urged to review these materials, including the technical reports filed with respect to the Company's mineral properties.

Cautionary Note Regarding References to Resources and Reserves

National Instrument 43 101 - Standards of Disclosure for Mineral Projects ("NI 43-101") is a rule developed by the Canadian Securities Administrators which establishes standards for all public disclosure an issuer makes of scientific and technical information concerning mineral projects. Unless otherwise indicated, all resource estimates contained in or incorporated by reference in this press release have been prepared in accordance with NI 43-101 and the guidelines set out in the Canadian Institute of Mining, Metallurgy and Petroleum (the "CIM") Standards on Mineral Resource and Mineral Reserves, adopted by the CIM Council on November 14, 2004 (the "CIM Standards") as they may be amended from time to time by the CIM.

United States shareholders are cautioned that the requirements and terminology of NI 43-101 and the CIM Standards differ significantly from the requirements and terminology of the SEC set forth in the SEC's Industry Guide 7 ("SEC Industry Guide 7"). Accordingly, the Company's disclosures regarding mineralization may not be comparable to similar information disclosed by companies subject to SEC Industry Guide 7. Without limiting the foregoing, while the terms "mineral resources", "inferred mineral resources", "indicated mineral resources" and "measured mineral resources" are recognized and required by NI 43-101 and the CIM Standards, they are not recognized by the SEC and are not permitted to be used in documents filed with the SEC by companies subject to SEC Industry Guide 7. Mineral resources which are not mineral reserves do not have demonstrated economic viability, and US investors are cautioned not to assume that all or any part of a mineral resource will ever be converted into reserves. Further, inferred resources have a great amount of uncertainty as to their existence and as to whether they can be mined legally or economically. It cannot be assumed that all or any part of the inferred resources will ever be upgraded to a higher resource category. Under Canadian rules, estimates of inferred mineral resources may not form the basis of a feasibility study or prefeasibility study, except in rare cases. The SEC normally only permits issuers to report mineralization that does not constitute SEC Industry Guide 7 compliant "reserves" as in-place tonnage and grade without reference to unit amounts. The term "contained ounces" is not permitted under the rules of SEC Industry Guide 7. In addition, the NI 43-101 and CIM Standards definition of a "reserve" differs from the definition in SEC Industry Guide 7. In SEC Industry Guide 7, a mineral reserve is defined as a part of a mineral deposit which could be economically and legally extracted or produced at the time the mineral reserve determination is made, and a "final" or "bankable" feasibility study is required to report reserves, the three-year historical price is used in any reserve or cash flow analysis of designated reserves and the primary environmental analysis or report must be filed with the appropriate governmental authority.

This press release is not, and is not to be construed in any way as, an offer to buy or sell securities in the United States.

NR10-32

Contacts:
International Tower Hill Mines Ltd.
Quentin Mai
Vice-President - Corporate Communications
1-888-770-7488 (toll free) or (604) 683-6332
(604) 408-7499 (FAX)
qmai@internationaltowerhill.com

International Tower Hill Mines Ltd.
Shirley Zhou
Manager - Corporate Communications
1-888-770-7488 (toll free) or (604) 638-3246
(604) 408-7499 (FAX)
szhou@internationaltowerhill.com
www.internationaltowerhill.com
 
casey zu den letzten beiden news:

Comments: The worst case NPV for the Livengood project in the above (at a conservative 7.5% discount rate, using $950 gold) is still well above the company's current market valuation, with a good IRR at 26.9%. The combined milling and leaching scenario requires more capital up front, but yields almost twice the NPV, and if you use $1200 gold, the NPV-7.5 goes to $2.2 billion and a 35.9% IRR. In short, unless the company is seriously misguided or dishonest, it's deeply undervalued.

Is it? We just sent Louis James to have a first hand look. He'll have more to say in the next issue of the International Speculator, but his due diligence report is highly favorable. The company has the right people, doing the right things to prove up the project's merit. We believe that as the company ticks off the engineering challenges, it will become increasingly attractive as a takeover target.

Best of all, the company has not soared with gold's recent gains. There is an "Alaska discount" that has a basis in the reality of the greater expense and difficulty of working in Alaska, but Louis reports that the phenomenal infrastructure advantages of the Livengood project are everything management has made them out to be, so we believe the discount is overdone on ITH. Consequently, we're changing our recommendation back to Buy on Weakness. With shares frequently trading below US$6.00 in recent weeks, that's what we'd shoot for, for an entry point.
 
http://www.ithmines.com/i/pdf/2010-09-27_NorthernMiner.pdf
 
International Tower Hill Mines Ltd. Announces Up To CAD 105,375,000 in Equity Financings
International Tower Hill Mines Ltd New ITH
9/28/2010 4:09:00 PM
VANCOUVER, Sep. 28, 2010 (Canada NewsWire via COMTEX News Network) --

/NOT FOR DISTRIBUTION TO UNITED STATES NEWS WIRE SERVICES OR FOR DISSEMINATION IN THE UNITED STATES/

International Tower Hill Mines Ltd. ("ITH" or the "Company") - (TSX: ITH, NYSE-A: THM, Frankfurt: IW9) is pleased to announce that the Company has entered into an agreement with Canaccord Genuity Corp. (the "Underwriter") pursuant to which the Underwriter has agreed to purchase, on a bought deal basis, pursuant to a short form prospectus (the "Public Offering"), 10,400,000 common shares of the Company (the "Common Shares") at a price of CAD 6.25 per Common Share for gross proceeds of CAD 65,000,000. In addition, the Company will grant the Underwriter an over-allotment option to purchase up to that number of additional Common Shares equal to 15% of the Common Shares sold pursuant to the Public Offering (maximum of 1,560,000 Common Shares), exercisable for a period of up to 30 days from the closing of the Public Offering (for additional gross proceeds of up to CAD 9,750,000).

The Underwriter will receive a cash commission of 5% of the gross proceeds raised under the Public Offering.

In addition, the Company will concurrently offer up to 4,900,000 common shares (the "Private Placement Common Shares" and together with the Common Shares, the "Offered Securities") at a price of CAD 6.25 per Private Placement Common Share through a non-brokered private placement (the "Private Placement") for gross proceeds of up to CAD 30,625,000. All Private Placement Common Shares issued will be subject to resale restrictions in Canada and the United States.

The Public Offering is anticipated to close on or before October 18, 2010 and is subject to certain conditions including, but not limited to, the completion of satisfactory due diligence by the Underwriter and the acceptance/approval of the Toronto Stock Exchange and the NYSE Amex. The Private Placement is also subject to the acceptance/approval of the Toronto Stock Exchange and the NYSE Amex and is expected to close concurrently with the Public Offering.

The Company intends to use the net proceeds from the two financings for continued work on its Livengood Gold project in Alaska and for general working capital purposes.

The Offered Securities have not been and will not be registered under the U.S. Securities Act of 1933, as amended (the "1933 Act") or any applicable state securities laws and may not be offered or sold in the United States or to, or for the account or benefit of, U.S. persons (as defined in Regulation S under the 1933 Act) or persons in the United States absent registration or an applicable exemption from such registration requirements. This press release shall not constitute an offer to sell or the solicitation of an offer to buy nor shall there be any sale of the Offered Securities in any jurisdiction in which such offer, solicitation or sale would be unlawful.

About International Tower Hill Mines Ltd.

International Tower Hill Mines Ltd. is a resource exploration company focused on the ongoing development of the advanced, multimillion-ounce gold discovery at Livengood in Alaska. ITH is committed to the aggressive development of the Livengood Project, thereby giving its shareholders the maximum value for their investment.

On behalf of

INTERNATIONAL TOWER HILL MINES LTD.

(signed) Jeffrey A. Pontius

Jeffrey A. Pontius, President and Chief Executive Officer
 
http://seekingalpha.com/article/228693-international-tower-hill-picking-up-the-pace?source=yahoo




...and would see Livengood produce an average 833,000 ounces of gold per year, making it larger than either Detour Lake or Canadian Malartic — the flagship assets of multi-billion dollar market darlings Detour Gold (DRGDF.PK) and Osisko Mining (OSKFF.PK).


International Tower Hill Mines (THM) recently announced up to C$105.4 million in equity financings in a serious attempt to pick up the pace at the Livengood project in Alaska. It's not that things have been progressing slowly -- the project went from early stage exploratory drilling in 2007 to preliminary economic assessment earlier this year. That is quite an accomplishment and management rightfully expected the market to recognize the progress.

Well, after many months of little traction in the share price, they finally gave up trying to go at it alone out of frustration at the lack of attention. Although moderately dilutive, the proposed financing will ensure that the money is there to take the project through feasibility and, perhaps just as importantly, that brokers like Cannacord will be on board to help spread the Livengood story to the market going forward.

The story is certainly a solid one. In an announcement last month, the company revealed that a staged heap-leach-only option at Livengood may generate a 7.5% discounted NPV of well over US$1 billion at current gold prices along with an IRR of over 50% based on an initial capital budget of US$638 million. Project development might be possible in an accelerated timeframe due to the property consisting of leased private and State of Alaska Mental Health Trust lands, the presence of nearby infrastructure and a straightforward (open pit heap leach) mining plan.

The company is also contemplating a combined large mill and heap leach operation, which is the scenario we assume in our detailed comparative analysis found below. Although this mining option is more sensitive to lower gold prices due to the significant capital cost of building a mill and tailings impoundment, initial capital expenditures are similar to the heap-leach-only option and would allow for the possibility of funding the expansion through cash flow. The large mill and heap leach mining scenario leads to a calculated NPV of over $2 billion at the current gold price and would see Livengood produce an average 833,000 ounces of gold per year, making it larger than either Detour Lake or Canadian Malartic — the flagship assets of multi-billion dollar market darlings Detour Gold (DRGDF.PK) and Osisko Mining (OSKFF.PK).

Besides the eventual recognition that should come from a positive feasibility study and mine development, International Tower Hill continues to conduct an aggressive exploration program designed to expand the Livengood deposit even further. This effort is being ignored by the market for now, but should the company successfully translate drilled meters to resource tonnage to longer mine life, a substantial near-term upward revaluation in the share price seems inevitable.

Peer Group Comparison


The following series of comparative valuation charts (click to enlarge) illustrate International Tower Hill's relative positioning among a chosen peer group of gold developers.
 
International Tower Hill Continues Expansion of the Core Zone at Depth at the Livengood Project, Alaska
Core Zone Infill Drilling Continues to Define Large, Higher Grade (+1 g/t Gold) Internal Zone (200 x 1000 Metres) and Extensions at Depth


http://www.marketwire.com/press-rel...-Livengood-Project-Alaska-TSX-ITH-1331405.htm


VANCOUVER, BRITISH COLUMBIA--(Marketwire - Oct. 7, 2010) - International Tower Hill Mines Ltd. (TSX:ITH)(NYSE Amex:THM)(FRANKFURT:IW9) ("ITH" or the "Company") is pleased to announce the results from the latest 20 holes completed in its 50,000-metre Summer 2010 Livengood Exploration Program (to see Fig. 1 please click on: http://media3.marketwire.com/docs/ith107.jpg). The infill portion of the Summer program is focused on conversion of resources to the measured and indicated categories as well as testing the down dip extension potential of the deposit. The Company is currently operating seven drills at Livengood (three RC and four core rigs).

Highlights of the ongoing 2010 work program at Livengood include:

Infill drilling continues to improve the definition of large higher grade areas within the overall deposit as indicated by holes MK-RC-0410 (97.5 metres of 1.11 g/t gold) and MK-RC-0414 (134.1 metres of 1.32 g/t gold) in the Core Zone. A higher grade area (+1 g/t gold) is being established in the Core Zone that is approximately 200 metres wide and a kilometre long. This expansion of the near surface higher grades reported last month (NR10-31) is anticipated to be the focus of initial production.
The Money Knob deposit at Livengood continues to expand laterally and several of the recent drill holes indicate a significant expansion of the Core Zone at depth.
The Company's pre-feasibility study is underway with ongoing hydrological studies, surface mine facility location analysis, phase 2 metallurgical studies (optimizing milling and heap leaching recoveries), deposit-scale geotechnical studies, and continuing environmental baseline data collection.
Core Zone Expansion at Depth

................................
 
Oct 19, 2010 14:42 ET
International Tower Hill Mines Ltd. Announces Launch of New Website

VANCOUVER, BRITISH COLUMBIA--(Marketwire - Oct. 19, 2010) - International Tower Hill Mines Ltd. ("ITH" or the "Company") (TSX:ITH)(NYSE Amex:THM)(FRANKFURT:IW9) is pleased to announce that the Company will be launching its new website on Wednesday, October 20, 2010. The new website represents a major overhaul and updating of its existing site to reflect the sole focus of the Company on the ongoing pre-feasibility study at the Livengood Project following the completion of the spin-out of its non-Livengood mineral projects to Corvus Gold Inc. (TSX:KOR), effective August 26, 2010.

In conjunction with the completion of the spin-out, the Company initiated a major review and updating of its existing website. In doing so, the Company identified that its existing website was not being updated on a regular basis, and has taken the appropriate steps, including expanding its corporate communications department with the addition of Ms. Shirley Zhou (see NR10-27), to ensure that the website is kept updated on a current basis. In addition, as part of its review of the Company's preliminary short form prospectus dated October 4, 2010, the British Columbia Securities Commission identified certain instances where the information disclosed by the Company on its existing website, including the Corporate Fact Sheet and its June 2010 and October 2010 Corporate Presentations, did not comply with NI 43-101 and other disclosure requirements. The Company therefore cautions investors that these materials should not be relied upon. The Company has removed these materials from the existing website, and NI 43-101 compliant versions will be posted on the new website.

About International Tower Hill Mines Ltd.

International Tower Hill Mines Ltd. is a resource exploration company focused on the ongoing pre-feasibility study for the multimillion-ounce gold discovery at Livengood in Alaska. ITH is committed to the aggressive advancement of the Livengood Project, thereby giving its shareholders the maximum value for their investment.

On behalf of INTERNATIONAL TOWER HILL MINES LTD.

Jeffrey A. Pontius, President and Chief Executive Officer
 
Nov 8 (Reuters) - International Tower Hill Mines Ltd:

* Rbc raises International Tower Hill Mines Ltd price target to C$9.50

from C$7; rating sector perform

For a summary of rating and price target changes on S&P 500 companies:

Reuters 3000Xtra users, double-click

Reuters Station users, click .1568

Reuters Plus users search on RCH/US

For a summary of rating and price target changes on non-S&P 500 companies:

Reuters 3000Xtra users, double-click

Reuters Station users, click .2102

Reuters Plus users search on RCH/US2

For a summary of rating and price target changes on Canadian companies:

Reuters 3000Xtra users, double-click

Reuters Station users, click .4899

Reuters Plus users search on RCH/CA

(Bangalore Equities Newsdesk +91 80 4135 5800; within U.S. +1 646 223 8780)

COPYRIGHT

Copyright Thomson Reuters 2010. All rights reserved.

The copying, republication or redistribution of Reuters News Content, including by framing or similar means, is expressly prohibited without the prior written consent of Thomson Reuters.



© 2010 AFX News
 
Nov 10, 2010 09:12 ET
International Tower Hill Mines Ltd. Announces Closing of CAD 105,375,000 in Equity Financings

VANCOUVER, BRITISH COLUMBIA--(Marketwire - Nov. 10, 2010) -

NOT FOR DISTRIBUTION TO UNITED STATES NEWS WIRE SERVICES OR FOR DISSEMINATION IN THE UNITED STATES

International Tower Hill Mines Ltd. ("ITH" or the "Company") - (TSX:ITH)(NYSE Amex:THM)(FRANKFURT:IW9) is pleased to announce that the Company has closed the bought deal short form prospectus financing announced September 28, 2010 (the "Offering"). The Company issued 10,400,000 common shares at a price of CAD 6.25 per common share for gross proceeds of CAD 65,000,000. The Underwriters (as defined below) also exercised their over-allotment option to acquire an additional 1,560,000 common shares for additional gross proceeds of CAD 9,750,000. Including the proceeds from the exercise of the over-allotment option, the total gross proceeds of the Offering were CAD 74,750,000.

The Offering was led by Canaccord Genuity Corp. and included BMO Nesbitt Burns Inc., GMP Securities Inc. and Salman Partners Inc. (the "Underwriters"). In connection with the Offering the Underwriters received a cash commission equal to 5% of the gross proceeds raised through the Offering.

In addition, the Company also announces the closing of a non-brokered private placement of 4,900,000 common shares at a price of CAD 6.25 per common share, for gross proceeds of CDN 30,625,000 (the "Private Placement"). No finder's fee was paid in connection with the Private Placement. All common shares issued in the Private Placement are subject to resale restrictions in Canada and the United States.

The Company intends to use the net proceeds from the two financings for continued work on its Livengood Gold project in Alaska and for general working capital purposes.

The securities described above have not been and will not be registered under the U.S. Securities Act of 1933, as amended (the "1933 Act") or any applicable state securities laws and may not be offered or sold in the United States or to, or for the account or benefit of, U.S. persons (as defined in Regulation S under the 1933 Act) or persons in the United States absent registration or an applicable exemption from such registration requirements. This press release shall not constitute an offer to sell or the solicitation of an offer to buy nor shall there be any sale of the foregoing securities in any jurisdiction in which such offer, solicitation or sale would be unlawful.

About International Tower Hill Mines Ltd.

International Tower Hill Mines Ltd. is a resource exploration company focused on the ongoing development of the advanced, multimillion-ounce gold discovery at Livengood in Alaska. ITH is committed to the aggressive development of the Livengood Project, thereby giving its shareholders the maximum value for their investment.

On behalf of INTERNATIONAL TOWER HILL MINES LTD.

Jeffrey A. Pontius, President and Chief Executive Officer
 
Nov 16, 2010 06:31 ET

International Tower Hill Defines Significantly Higher Grade Near Surface Zones at Livengood Project, Alaska


VANCOUVER, BRITISH COLUMBIA--(Marketwire - Nov. 16, 2010) - International Tower Hill Mines Ltd. (TSX:ITH)(NYSE Amex:THM)(FRANKFURT:IW9) -

Highlights

MK-10-62: 18.4m @ 4.2 g/t & 17 m @ 2.4 g/t gold – Core Zone Infill
MK-RC-0440: 15.m @ 3.1 g/t gold – Core Zone Infill
MK-RC-0448: 47.3m @ 1.8 g/t gold – Core Zone Infill
MK-RC-0438: 38.1m @ 1.7 g/t & 12.2 m @ 4.6 g/t gold – Core Zone Infill
MK-RC-0449: 74.7m @ 1.3 g/t gold – Core Zone Infill
MK-10-64: 75.9m @ 1.1 g/t & 3.4m @ 8.3 g/t gold – Sunshine Zone Infill
MK-RC-0429: 77.7m @ 1.0 g/t gold – Core Zone Infill

International Tower Hill Mines Ltd. ("ITH" or the "Company") is pleased to announce the results from the latest 30 holes completed in its 55,000-metre Summer 2010 Livengood Exploration Program (Figure 1: http://media3.marketwire.com/docs/ith-map1.pdf). The Summer 2010 program is focused on the conversion of the existing NI 43-101 indicated and inferred resources to the measured and indicated categories through infill drilling, as well as step-out resource expansion and mine development-related engineering and environmental testing. The Company is currently operating seven drills at Livengood (three RC and four core rigs).

Highlights of the ongoing 2010 work program at Livengood include:

Infill drilling continues to expand and add greater definition of near surface, higher grade areas in the Core and Sunshine zones. Recent results continue to outline significant zones of higher grade mineralization in the top 150 metres of the deposit, which will be the key economic drivers of starter pit design work in the coming months. Several significant intervals highlighted in this news release in this shallow zone are: MK-RC-0448, 47m @ 1.76 g/t gold beginning at 96 metres; MK-RC-0446, 32m @ 1.39 g/t gold beginning at 78 metres; MK-RC-0440 15m @ 3.11 g/t gold beginning at 24 metres; MK-RC-044, 1 27m @ 1.09 g/t gold & 31m @ 1.57 g/t gold beginning at 11 metres and MK-10-62, 18m @ 4.18 g/t gold & 71m @ 0.98 g/t gold beginning at 67 metres.
Completion of infill drill holes below the floor of prior drilling (approximately 300 metres in depth) in the Core Zone continues to expand this dimension of the deposit. Ten of 18 Core Zone drill holes reported in this news release have significant intercepts below the general floor of previous drilling (MK-RC-0432, 17m @ 1.85 g/t gold beginning at 384 metres; MK-RC-0443, 15m @ 1.08 g/t gold beginning at 299 metres; MK-RC-0440, 11m @ 1.08 g/t gold beginning at 291 metres).

.
.
.

http://www.marketwire.com/press-rel...r-Surface-Zones-Livengood-TSX-ITH-1354027.htm
 
New Purchase: International Tower Hill Mines Ltd (THM)

John Paulson initiated holdings in International Tower Hill Mines Ltd. His purchase prices were between $5.84 and $6.58, with an estimated average price of $6.17. The impact to his portfolio due to this purchase was 0.14%. His holdings were 5,000,000 shares as of 09/30/2010.

International Tower Hill Mines Ltd. is a Canada-based resource exploration company possessing a portfolio of Alaskan and Nevada based gold and base metal exploration projects. International Tower Hill Mines Ltd has a market cap of $547.2 million; its shares were traded at around $8.04 .



http://www.gurufocus.com/news.php?id=114342



http://www.ibtimes.com/articles/82500/20101116/paulson-hedge-fund-stocks-financials.htm

Who is John Paulson: http://en.wikipedia.org/wiki/John_Paulson

"Paulson & Co., Inc., is the manager of several hedge funds, which are loosely regulated investment funds. Paulson's firm had assets under management (as of June 1, 2007) of $12.5 billion (95% from institutions), which leapt to $36 billion as of November 2008"

Share Structure

As at November 15, 2010:

Shares Outstanding: 84,503,155
Shares Fully Diluted: 90,753,155
 
Intl Tower Hill Target Raised To C$12.30 From C$8.75 By Canaccord Genuity

International Tower Hill (ITH-T8.30-0.15-1.78%) has a strong balance sheet in a robust gold environment, said Canaccord Genuity analyst Wendell Zerb. It recently closed a $105.4-million (Canadian) private placement, providing sufficient capital to advance its key Livengood project.
Upside: “We are reiterating our ‘speculative buy’ recommendation on International Tower Hill and increasing our 12-month target to $12.30 from $8.75,” he wrote.
 
Nov 29, 2010 16:38 ET
International Tower Hill Mines Intersects 112 Metres of 2.63 g/t Gold at the Livengood Gold Project, Alaska

VANCOUVER, BRITISH COLUMBIA--(Marketwire - Nov. 29, 2010) - International Tower Hill Mines Ltd. (TSX:ITH)(NYSE Amex:THM)(FRANKFURT:IW9) -

Higher grade results located in Core Zone near edge of SW Zone suggest continued resource extension to be determined during 2011 Winter drill program
RC Hole 458: 112 metres @ 2.63 g/t gold (includes 64 metres @ 3.4 g/t gold) & 108.2 metres @ 1.0 g/t gold
RC Hole 452: 85 metres @ 1.12 g/t gold & 188 metres @ 0.96 g/t gold
RC Hole 445: 68 metres @ 1.26 g/t gold (includes 13.7 metres @ 2.58 g/t gold)


International Tower Hill Mines Ltd. ("ITH" or the "Company") - (TSX:ITH)(NYSE Amex:THM)(FRANKFURT:IW9) is pleased to announce the results of the latest 14 holes from its 65,000-metre 2010 Livengood Drilling Program (To view Figure 1, please click on the following link: http://media3.marketwire.com/docs/1129tower.jpg). Extensive infill and deep drilling in the southern part of the Core Zone has intersected the highest grade gold mineralization over the largest intercepts on the project to date below the floor of earlier grid drilling. Significantly, results from RC holes 458, 452 and 445 along the Southwest boundary of the Core Zone demonstrate a possible extension into the SW Zone, which will be the focus of the upcoming 2011 Winter Drill program.

In the southwest section of the Core Zone, drill hole MK-RC-0458 intersected a thick interval of higher grade mineralization (112 metres of 2.63 g/t gold) from what appears to be a broad feeder zone. This and previous intersections suggest the possibility of higher grade mineralization covering an area at least 400 metres by 400 metres and extending into the SW Zone.

In addition, the latest drill results continue to identify higher grade mineralization within the upper oxide zone of the deposit with intercepts of 85.3 metres of 1.1 g/t gold (hole MK-RC-0454) and 13.7 metres of 2.6 g/t gold (hole MK-RC-0452). These higher grade zones are anticipated to form the basis of a high-grade starter pit when they are integrated into an updated Money Knob resource estimate currently scheduled to be completed in the first quarter of 2011.

The Company continues to carry out a comprehensive development drilling program of condemnation and geotechnical work at the Livengood Project, as well as extensive optimization studies in mine and process design, metallurgy, and environmental characterization.

.
.
.

http://www.marketwire.com/press-rel...ld-Livengood-Gold-Project-TSX-ITH-1360645.htm
 
http://www.benzinga.com/analyst-ratings/analyst-color/10/11/632619/dahlman-rose-reiterates-buy-rating-on-international-tower
 
Dec 08, 2010 09:16 ET
International Tower Hill Mines Advances Livengood Gold Project Towards Potential Production Decision with Prefeasibility Study and Augmented Development Team

VANCOUVER, BRITISH COLUMBIA--(Marketwire - Dec. 8, 2010) - International Tower Hill Mines Ltd. ("ITH" or the "Company") (TSX:ITH)(NYSE Amex:THM)(FRANKFURT:IW9) is pleased to provide an operational update at its Livengood Gold Project near Fairbanks, Alaska. To date, the Company has achieved key milestones in advancing the Livengood project's pre-feasibility study (PFS) and adding key members to its development team.

Highlights include:

*

Awarding of major contracts for the Livengood pre-feasibility study;
*

Continued augmentation of in-house development and permitting staff;
*

Optimization studies for maximizing the value of the deposit and improving operational characteristics, inclusive of an oxide milling option which brings higher recoveries and greater reliability to the production plan;
*

Continued drilling focused on advancing key development-related projects such as surface facility characterization, hydrology and metallurgy;
*

Continued drilling focused on resource infill and step out work as well as the calculation of a new resource base with the addition of over 50,000 metres of new drilling in 2010; and
*

Planning of a new district-scale exploration program for the potential discovery of new deposits along a 10-kilometre-long surface gold trend on the Company's extensive 145 km2 Livengood land package.

Jeff Pontius, CEO of ITH, stated: "I am very pleased with the rapid advancement of the Livengood project toward our corporate goal of creating the next new mid-tier gold producer. The project is hitting its milestones as planned, and I am most encouraged by the excellent team we are assembling to take our Company through the pre-feasibility/feasibility stage and on to a potential production decision."

Pre-feasibility Study

Over the past three months, the Company has awarded key contracts for the PFS to:

*

FLSmidth Salt Lake City, Inc. of Salt Lake City, Utah, for metallurgical engineering and design of processing plants, and to act as the lead author for both the PFS final report and the resulting NI 43-101 technical report;
*

Knight Piesold & Co. of Denver, Colorado, for direction of studies on site location, geotechnical characterization and design of waste rock storage, heap leach pad, tailings storage facilities, and water storage reservoirs;
*

Mine Development Associates of Reno, Nevada, to perform mine engineering;
*

SRK Consulting of Denver, Colorado, to perform pit geotechnical design, groundwater hydrogeology and rock geochemistry studies; and
*

MTB Project Management Professionals, Inc. to support ITH in the management and integration of all studies.

Augmentation of Development Team

The Company has also strengthened its corporate and technical management structure with the following appointments:

*

Carl Brechtel has been appointed as President, in addition to his position as Chief Operating Officer, in order to bring greater focus on the operating aspects of the Company. Jeffrey Pontius will continue as the Company's CEO, focusing on corporate strategy and marketing.
*

Karl Hanneman has been appointed as General Manager, Livengood Project, and has expanded the Fairbanks Project Management Team to include Richard Moses as Site Operations Manager, Keith Malone as Technical Services Manager, Chris Puchner as Chief Geologist and Denise Hertzog as Environmental Manager.

Carl Brechtel, newly appointed President and COO of ITH, stated: "The PFS Team brings extensive experience in the major technical areas of mining project design and will make a major, positive contribution to the optimization of the Livengood Project. In addition, the Company has created a Fairbanks project group that has extensive operating and project development experience in Alaska and who are known and respected in the local community."

Drilling Progress at Livengood

The Company's Winter and Summer 2010 drill programs at Livengood are projected to reach 70,000 metres by the end of the year and will produce technical information for resource evaluation, hydrogeologic characterization, geotechnical characterization, metallurgical characterization and site condemnation. Key project development studies have been accelerated into the third and fourth quarters of 2010, with geotechnical characterization work being conducted through the winter season. Preparation of heap leach column tests was accelerated into the fourth quarter of 2010 due to early completion of PQ core drilling and excavation of a run-of-mine sample for large diameter column tests. The preparation of the leach columns is currently underway at McClelland Labs in Reno, Nevada.

In addition, the 2010 drilling has expanded the deposit at depth as well as to the southwest and the results will form the basis of an updated resource estimation projected to be released in the first quarter of 2011.

The Company has now moved drilling activities to a year-round basis in 2010 and will continue on this schedule in 2011. An extensive $2.5 million district-wide exploration program will be added to Livengood activities during 2011. This effort will be augmented with a district-wide 3-D Induced Polarization geophysical survey to aid in new deposit targeting. The main deposit exploration drilling efforts will begin in early February and focus on the western extension of the deposit as well as evaluation of the extent of the newly discovered deep zone announced last week (NR10-38).

Livengood Project Highlights

*

Drilling at the project continues to expand the deposit, with the current estimated resource only representing a snapshot in time. The latest resource estimate (as at June 22, 2010) of 409 Mt at an average grade of 0.83 g/t gold (10.9 Moz Indicated) and 94 Mt at an average grade of 0.79 g/t gold (2.4 Moz Inferred), both at a 0.5 g/t gold cut-off grade, make it one of the largest new gold discoveries in North America.
*

The Core and Sunshine Zones together account for most of the higher grade mineralization (Indicated Resources of 202 Mt at an average grade of 1.07 g/t gold and Inferred Resources of 40 Mt at an average grade of 1.06g/t gold, based on a cut-off grade of 0.70 g/t gold) and will form the basis for starter pit design work.
*

The PFS will include work for processing alternatives to identify those that have potential to make significant positive impacts on project economics.
*

The geometry of the currently defined shallowly dipping, outcropping deposit has a low strip ratio amenable to low cost open pit mining which could support a high production rate and economies of scale.
*

No major permitting hurdles have been identified to date.
*

The Livengood project has a very favourable logistical location, being situated 110 road kilometres north of Fairbanks, Alaska along the paved, all-weather Elliott Highway, the Trans-Alaska Pipeline Corridor, and the proposed Alaska natural gas pipeline route. The terminus of the Alaska State power grid lies approximately 80 kilometres to the south.
*

ITH controls 100% of its approximately 145 square kilometre Livengood land package, which is made up of fee land leased from the Alaska Mental Health Trust, a number of smaller private mineral leases and 115 Alaska state mining claims.

Geological Overview

The Livengood Deposit is hosted in a thrust-interleaved sequence of Proterozoic to Palaeozoic sedimentary and volcanic rocks. Mineralization is related to a 90 million year old (Fort Knox age) dike swarm that cuts through the thrust stack. Primary ore controls are a combination of favourable lithologies and crosscutting structural zones. In areas distal to the main structural zones, the selective development of disseminated mineralization in favourable host rocks is the main ore control.

Within the primary structural corridors, all lithologies can be pervasively altered and mineralized. Devonian volcanic rocks and Cretaceous dikes represent the most favourable host lithologies and are pervasively altered and mineralized throughout the deposit. Two dominant structural controls are present: 1) the major shallow south-dipping faults which host dikes and mineralization which are related to dilatant movement on structures of the original fold-thrust architecture during post-thrusting relaxation, and 2) steep NW trending linear zones which focus the higher-grade mineralization which cuts across all lithologic boundaries. The net result is broad flat-lying zones of stratabound mineralization around more vertically continuous, higher grade core zones with a resulting lower strip ratio for the overall deposit and higher grade areas that could be amenable for starter pit production.

The surface gold geochemical anomaly at Livengood covers an area 6 kilometres long by 2 kilometres wide, of which approximately half has been explored by drilling to date. Surface exploration is ongoing as new targets are being developed to the northeast and west of the known deposit.

Qualified Person and Quality Control/Quality Assurance

Exploration and development work at the Livengood Project is directed by Carl E. Brechtel (Colorado PE 23212, Nevada PE 8744) who is a qualified person as defined by National Instrument 43-101. He is a member of AusIMM and SAIMM. Mr. Brechtel has supervised the preparation of the scientific and technical information that forms the basis for this news release and has approved the disclosure herein. Mr. Brechtel is not independent of ITH, as he is the President and COO of the Company and holds incentive stock options.

The Livengood exploration program is designed and supervised by Chris Puchner, Chief Geologist (CPG 07048) of the Company, who is responsible for all aspects of the work, including the quality control/quality assurance program. Mr. Puchner is not independent of ITH as he is an employee and holds shares and incentive stock options.

On-site personnel at the project photograph the core from each individual borehole prior to preparing the split core. Duplicate reverse circulation drill samples are collected with one split sent for analysis. Representative chips are retained for geological logging. On-site personnel at the project log and track all samples prior to sealing and shipping. All sample shipments are sealed and shipped to ALS Chemex in Fairbanks, Alaska, for preparation and then on to ALS Chemex in Reno, Nevada or Vancouver, B.C. for assay. ALS Chemex's quality system complies with the requirements for the International Standards ISO 9001:2000 and ISO 17025:1999. Analytical accuracy and precision are monitored by the analysis of reagent blanks, reference material and replicate samples. Quality control is further assured by the use of international and in-house standards. Finally, representative blind duplicate samples are forwarded to ALS Chemex and an ISO compliant third party laboratory for additional quality control.

About International Tower Hill Mines Ltd.

International Tower Hill Mines controls a 100% interest in the world-class Livengood Gold Project accessible by paved highway 70 miles north of Fairbanks, Alaska. ITH is focused on the rapid advancement of the project into a compelling potential development project in 2011 while it continues to expand its current resource and explore its 145 km2 district for new deposits.
 
Alaskan Gold: A New Super-Deposit in the Making?
Marc Davis
Published 12/7/2010


Though gold discoveries in Latin America and other far-flung locations have been lighting up the stock markets lately, Alaska is now earning back some of the limelight.
This is where over 115 million ounces of gold have been outlined in America’s last mineral frontier by three high-flying gold developers, namely Novagold Resources, Northern Dynasty Minerals and International Tower Hill Mines.

The latest development to illustrate how their world class discoveries rival the best on offer anywhere else in the world involves a new high-grade discovery zone at the emerging 10.9 million ounce Livengood gold deposit in politically stable, pro-mining central Alaska. Wholly owned by International Tower Hill Mines (NYSE-AMEX: THM) (TSX: ITH), the deposit is located 70 miles north of Fairbanks, Alaska.
Last week, the company (ITH) announced its best drill results to date. This new development could lead to a significant expansion of what by global standards is already an unusually large asset, according to company CEO Jeff Pontius.
With drilling highlights that include 112 meters of 2.63 grams per tonne of gold, he adds that ITH is now tapping into previously unexplored deeper gold mineralization, which is still shallow enough to be amenable to cost-efficient open pit mining.
“This all bodes well for what could evolve into a major resource expansion of the deposit,” he says
Several mining analysts who have studied ITH’s recent drill results concur with Pontius, at least in terms of acknowledging their potential to enrich the overall value of the deposit. They include Toronto-based Alex Terentiew of the global investment bank, Credit Suisse.
“…the high grades lead us to suspect there is good potential for the average grade of the deposit to be enhanced,” Terentiew says. “As the deposit is designed as a bulk tonnage, low grade mine, an increase in the average life-of-mine grade can have a substantial impact on the project economics.”
A pre-feasibility study (an initial blueprint for a mine) is underway at Livengood and is expected to be completed by the fall of 2011. By that time ITH hopes to have outlined considerably more gold, Pontius says.

He adds that the prolific size of the deposit has already attracted potential takeover candidates. They include some of the world’s largest gold miners, all of which are scrambling to replenish dwindling gold inventories. This is proving to be a daunting challenge against a backdrop of a global decade-long trend of falling output numbers, which have been consistently dropping at around 5% per annum.
Hence, the world’s well-established gold producers – emboldened by strong balance sheets – are all focused on ramping-up their production figures to continue to cash in on a secular bull market in bullion prices. So says Michael Jalonen, a Toronto-based mining analyst for Bank of America Merrill Lynch, the US investment bank.
In a recent research report entitled “Global Gold M&A Heats Up”, he says that these gold miners cannot rely on organic growth, alone, and that they stand to grow much faster by making acquisitions.
“…we expect the reserve-hungry senior and mid-tier producers to continue focusing their attention on resource-rich junior producers and developers,” Jalonen adds.
“By our count, the top ten gold producers under coverage will need to replace 38 million ounces of gold reserves mined in 2010,” he says. “We estimate the biggest gold companies could generate $80 billion of free cash flow over the 2010-2015 period that could be deployed for acquisitions.”
Pontius is remaining tight-lipped as to who ITH’s suitors actually are. However the 5.4 million ounce Fort Knox Mine, which is owned by mining powerhouse Kinross Gold Corp. (TSX: K) (NYSE: KGC), lies just 60 miles southeast of the Livengood project.

The Fort Knox mine is expected to wind down by the time Livengood may be ready for commercialization. And Kinross has extensive gold processing infrastructure already in place that could be of value to ITH, assuming the project gets the go-ahead to become a mine in 2016 or the following year.

Such a scenario makes Kinross an obvious strong contender to gobble up ITH, according to Wendell Zerb, a Vancouver-based mining analyst for the stock brokerage firm, Canaccord Genuity.
“Kinross is a very logical potential candidate for being interested in Livengood,” he says. “But given the size of the deposit, there could be a fit with a number of different major gold mining companies.”
The overall size of Livengood’s growing asset base is already a strong selling point as major mining companies are known to prefer deposits that can yield significant amounts of gold year after year – ones that can have a meaningful impact on their bottom line.
And 10-million-ounce-plus deposits are becoming increasing rare worldwide, according to Zerb, who adds that Livengood is “one of only a few very large gold assets with considerable upside leverage in a strong gold environment (greater than US $1,100/oz)."

This view is shared by Michael Curran, a Toronto-based mining analyst for the major Canadian investment bank, RBC Capital Markets.

“In our view, International Tower Hill has been one of the better exploration success stories over the past few years,” he says. “With potential for resource increases…we see above average potential for the deposit to ultimately be developed as a large open pit mine capable of producing +500,000 oz/yr.”
 
John Hathaway: Get Over Gold's Rise and Get In

by: Jeff Clark - December 16, 2010| about:GLD / OSKFF.PK / SLV / THM

http://seekingalpha.com/article/242167-john-hathaway-get-over-gold-s-rise-and-get-in?source=yahoo

When John Hathaway spoke at the Casey’s Gold and Resource Summitin October, many of the
audience came away feeling like they werelistening to Doug Casey, with his contrarian views, bold
statements,and laying much of the blame for our current problems at the feet ofgovernment. Read
what John, a seasoned investment pro and manager of thefamously successful $1.4 billion Tocqueville
Gold Fund, has to sayabout gold, precious metals stocks, and the future of the U.S. dollar.


A BIG GOLD interview with John Hathaway, Tocqueville Gold Fund..

..

Jeff: So the fund invests quite a bit in juniors.

John:Absolutely. We have to be careful with it, of course, because they're less liquid and riskier,
but the fact that we have this sort of database of information from these meetings gives us a fair
amount of success in terms of picking the good ones. Obviously there are plentywe've missed that
are good, and there are plenty we've invested in that turned out not to be so great, so it's always a
bit of atrial-and-error thing. But we have found that when we buy into a company at an early stage
that meets its milestones and advances
from Ato B and then from B to C, they’ll need more money
and we'll continue to finance them along the way. That is the single biggest source of our success.

Our turnover rate is very low – less than 10%– so we basically take a long-term investment view
on what we think are the very best emerging mining companies.
An example would be Osisko
(OSKFF.PK),which we started financing five or six years ago when it was a 50-cent junior, and now
it's a $14 company, which will be producing gold within a year. That's the ideal progression we like
to find.


Jeff: Any companies that look particularly undervalued to you right now?

John: We have a big position in International Tower Hill Mines (THM),which we feel is on the cusp of
becoming recognized as one of the next big major mines in North America.
I would put Osisko in
the same sentence, though it's obviously much further along than ITH
. I wouldn't necessarily run out
and buy these today, but those are big holdings for us and have done very well.
 
Oben Unten