Rohstoffthread (Archiv)

Status
Für weitere Antworten geschlossen.
5/8/2008 1:00:03 AM ET News Release Index

Mustang Reports Positive Results From Prefeasibility Study at Maskwa Open Pit Nickel Project

TORONTO, ONTARIO, May 8, 2008 (Marketwire via COMTEX News Network) --

Mustang Minerals Corp., (TSX VENTURE:MUM)(FRANKFURT:NJF) today announced positive results from the prefeasibility study completed for the Company's Maskwa nickel-copper-platinum group metals project located near Lac du Bonnet Manitoba. The study was compiled by Micon International Limited with Met-Chem Canada Inc. Wardrop Engineering Inc and Golder Associates Ltd. The proposed project is a 2,750 tonnes per day open pit mine and milling operation producing an average of 9.2 million pounds of nickel per year in concentrate and other credits including platinum group metals, copper and cobalt. Micon concluded that " the Maskwa Project contains an economic mineral reserve and warrants continued development to the full feasibility stage."

Mustang President Robin Dunbar commented that "the prefeasibility study outlines important progress made to date on the mine development and highlights the potential for Maskwa to be a low cash cost producer of nickel. The project has exceptional upside from here including the potential for more in pit resource and by incorporating Mustang's large Mayville resource."

Using the exchange rate and metal price assumptions contained herein the Project is projected to yield a pre-tax internal rate of return (IRR) of 19.4 % and a NPV of C$62.2 million at an 8% discount rate. The undiscounted pre-tax operating profit generated by the project is C$285 million with peak single year pre-tax earnings of $63 million. Net life-of-mine revenue for the project after smelting and refining charges is $569 million. Operating cost per tonne milled averages $39.54 for the life of the project. Cash cost of nickel produced net of credits is CDN$ 2.77 per pound. The initial capital cost of the project is C$123 million including contingency of C$10.6 million.

Wardrop Engineering Inc. (Wardrop) estimated a Proven and Probable open pit reserve totalling 7.11 million tonnes grading 0.64% nickel, 0.13% copper, 0.01% cobalt, 0.10 g/t platinum and 0.37 g/t palladium. The reserve is based on a diluted nickel cut-off of 0.2% nickel. A two phase open pit design was incorporated. Total waste tonnes in phase 1 were 15.54 million tonnes for a strip ratio of 5.5:1. The strip ratio for phase 1 and 2 combined is 10.8:1. The reserve was derived from a geological resource of Measured and Indicated resources of 10.12 million tonnes grade 0.60% nickel, 0.12% copper, 0.105% cobalt, 0.38 grams/tonne palladium and 0.10 grams/tonne platinum.

Based on infill sampling programs carried out in recent months by the Company, Wardrop has noted that strong potential exists for adding additional mineralization from both the "hangingwall" of the pit and the main zone of mineralization. Wardrop suggests that a new geological model for mineralization be created and verified with additional drill holes and further infill sampling of historic drill holes available to the company.

The economic analysis uses the assumption of a US$ 10 per pound nickel price in the first 2 years (based on the assumption that the first two years' production could be hedged) reverting to a long term metal price of $8 per pound. The resulting average prices predicted for the life of the project, expressed in 2007 dollars, are nickel $8.57 (U.S.) per pound, copper $2.42 (U.S.) per pound, cobalt $20 (U.S.) per pound, platinum $ 1,500 (U.S.) per ounce and palladium $ 359.70 (U.S.) per ounce. The base exchange rate assumed for the economic model is Canadian-dollar/U.S.-dollar equals 0.90.

Processing of the ore is to be by standard grinding and flotation techniques. Most of the comminution test work was by SGS Mineral Services of Lakefield Ontario. Metallurgical recoveries used in the study were based on extensive test work conducted at Process Research Associates in Richmond B.C. under the supervision of F. Wright Consulting Inc. Most of the associated analytical work was performed by iPL Laboratories which has ISO 9001 accreditation with check analyses performed by ACME labs of Vancouver BC. Testwork included both open cycle and locked cycle tests. The predicted plant recoveries of 72% nickel, 81 % copper, 71% cobalt, 47% platinum and 82% palladium were based on a locked cycle test that produced an average concentrate grade of 10.2% nickel, 2.5% copper, 0.36% cobalt 9.8 g/t palladium and 1.5 g/t platinum. This concentrate also contained approximately 33% S, 35% Fe and 5.4% MgO. Smelting and refining charges were based on indicative terms received from a Sudbury smelter and refiner of nickel and associated metals. The report of F.Wright Consulting concluded that "Based on more recent open cycle studies... further improvements to recovery may be available by modifications to the reagent scheme."

Initial capital cost (but not including sustaining capital) for the project including contingency is estimated to be $123 million. Major cost components include plant and infrastructure at $65.6 million; mining equipment at $29.4 million; EPCM and owners costs of $13.2 million; tailings and water management of $4 million and contingency of $10.6 million. The plant and infrastructure was designed for an average throughput of 2,750 tonnes of ore per day. Met-Chem Canada Inc. completed the plant and infrastructure design as well as capital cost and operating costs estimation for the plant. Power will be accessed from the Manitoba Hydro grid.

Baseline environmental studies are well advanced in the project area and the Company will soon commence public engagement for the project leading to a formal permit application. Tailings and water management facilities were designed by Golder Associates Ltd.

Mustang Proceeding with Full Feasibility Study

The Mustang board of directors has approved that a full feasibility study be completed and a mine permit be applied for at the Maskwa Project. Currently additional work at the project is focused on in-pit resource expansion. Mustang has completed drilling additional drill holes in the area of the proposed Maskwa Open Pit and has completed additional sampling of available historical holes. Based on the results of this work a new resource will be calculated for inclusion in the full feasibility study. Mustang will also investigate supplying open pit feed from the Mayville M2 resource to further enhance the economics and mine life of the Maskwa project.

The external Qualified Persons for purposes of National Instrument 43-101 are:

Micon International Inc. - Ian Ward P.Eng, Chris Jacobs C.Eng.

Wardrop Engineering Inc, - Cliff Duke, P.Eng., Chris Sharpe, P.Eng.

Met-Chem Canada Inc.- Lionel Poulin Eng.

F.Wright Consulting Inc. - Frank Wright P. Eng.

Golders Associates Ltd.- Irwin Wislesky, P.Eng.

About Mustang Minerals Corp. - Base Metal Resources

Mustang owns 100% of the mineral rights to Maskwa subject to a 1% Net Smelter Royalty with no obligations for offtake or back-in rights held by a third party. Mustang also owns the mineral rights to the Mayville Property which is located 35 km by road from Maskwa. The geological resource at the Mayville M2 Zone consists of an open pit Indicated Resource of 21.9 million tonnes grading 0.20% nickel and 0.48% copper containing 94.3 million pounds of nickel and 232 million pounds of copper. The M2 resource was prepared by Scott Wilson Roscoe Postle Associates in January 2007. (for technical notes please see Feb.7, 2008 press release).

Carey Galeschuk P. Geo and Ernie Marcotte P. Eng are the Qualified Person for Mustang Minerals Corp. for purposes of National Instrument 43-101.

To find out more about Mustang Minerals Corp. (TSX-V: MUM) visit our website at www.mustangminerals.com or contact: David Black, Investor Relations Telephone (416) 955-4773 email: info@mustangminerals.com

We seek safe harbour.

This news release contains forward-looking statements within the meaning of the United States Private Securities Litigation Reform Act of 1995 and forward-looking information within the meaning of the Securities Act (Ontario) (together, "forward-looking statements"). Such forward-looking statements may include the Company's plans for its mineral projects in Manitoba, the overall economic potential of its properties, the availability of adequate financing and involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements expressed or implied by such forward-looking statements to be materially different. Such factors include, among others, risks and uncertainties relating to potential political risk, uncertainty of production and capital costs estimates and the potential for unexpected costs and expenses, physical risks inherent in mining operations, currency fluctuations, fluctuations in the price of nickel and other metals, completion of economic evaluations, changes in project parameters as plans continue to be refined, the inability or failure to obtain adequate financing on a timely basis, and other risks and uncertainties, including those described in the Company's Management Discussion and Analysis for the period ended December 31, 2007 and Material Change Reports filed with the Canadian Securities Administrators and available at www.sedar.com.

The Company advises investors that although certain terms contained herein are recognized and required by Canadian securities regulations (under National Instrument 43-101 "Standards of Disclosures for Mineral Projects"), the US Securities and Exchange Commission does not recognize these terms.

Shares Outstanding: 72,407,427

SOURCE: Mustang Minerals Corp.

Mustang Minerals Corp. David Black Investor Relations (416) 955-4773 Email: info@mustangminerals.com Website: www.mustangminerals.com
Copyright (C) 2008 Marketwire. All rights reserved.

instinformer.php
 
Eure Einschätzung zur Studie?

- Profitabilität gegeben
- Upsidepotential
- Minenkosten nicht zu hoch

Gefällt mir gut!

[url=http://peketec.de/trading/viewtopic.php?p=396203#396203 schrieb:
dukezero schrieb am 08.05.2008, 07:42 Uhr[/url]"]5/8/2008 1:00:03 AM ET News Release Index

Mustang Reports Positive Results From Prefeasibility Study at Maskwa Open Pit Nickel Project

TORONTO, ONTARIO, May 8, 2008 (Marketwire via COMTEX News Network) --

Mustang Minerals Corp., (TSX VENTURE:MUM)(FRANKFURT:NJF) today announced positive results from the prefeasibility study completed for the Company's Maskwa nickel-copper-platinum group metals project located near Lac du Bonnet Manitoba. The study was compiled by Micon International Limited with Met-Chem Canada Inc. Wardrop Engineering Inc and Golder Associates Ltd. The proposed project is a 2,750 tonnes per day open pit mine and milling operation producing an average of 9.2 million pounds of nickel per year in concentrate and other credits including platinum group metals, copper and cobalt. Micon concluded that " the Maskwa Project contains an economic mineral reserve and warrants continued development to the full feasibility stage."

Mustang President Robin Dunbar commented that "the prefeasibility study outlines important progress made to date on the mine development and highlights the potential for Maskwa to be a low cash cost producer of nickel. The project has exceptional upside from here including the potential for more in pit resource and by incorporating Mustang's large Mayville resource."

Using the exchange rate and metal price assumptions contained herein the Project is projected to yield a pre-tax internal rate of return (IRR) of 19.4 % and a NPV of C$62.2 million at an 8% discount rate. The undiscounted pre-tax operating profit generated by the project is C$285 million with peak single year pre-tax earnings of $63 million. Net life-of-mine revenue for the project after smelting and refining charges is $569 million. Operating cost per tonne milled averages $39.54 for the life of the project. Cash cost of nickel produced net of credits is CDN$ 2.77 per pound. The initial capital cost of the project is C$123 million including contingency of C$10.6 million.

Wardrop Engineering Inc. (Wardrop) estimated a Proven and Probable open pit reserve totalling 7.11 million tonnes grading 0.64% nickel, 0.13% copper, 0.01% cobalt, 0.10 g/t platinum and 0.37 g/t palladium. The reserve is based on a diluted nickel cut-off of 0.2% nickel. A two phase open pit design was incorporated. Total waste tonnes in phase 1 were 15.54 million tonnes for a strip ratio of 5.5:1. The strip ratio for phase 1 and 2 combined is 10.8:1. The reserve was derived from a geological resource of Measured and Indicated resources of 10.12 million tonnes grade 0.60% nickel, 0.12% copper, 0.105% cobalt, 0.38 grams/tonne palladium and 0.10 grams/tonne platinum.

Based on infill sampling programs carried out in recent months by the Company, Wardrop has noted that strong potential exists for adding additional mineralization from both the "hangingwall" of the pit and the main zone of mineralization. Wardrop suggests that a new geological model for mineralization be created and verified with additional drill holes and further infill sampling of historic drill holes available to the company.

The economic analysis uses the assumption of a US$ 10 per pound nickel price in the first 2 years (based on the assumption that the first two years' production could be hedged) reverting to a long term metal price of $8 per pound. The resulting average prices predicted for the life of the project, expressed in 2007 dollars, are nickel $8.57 (U.S.) per pound, copper $2.42 (U.S.) per pound, cobalt $20 (U.S.) per pound, platinum $ 1,500 (U.S.) per ounce and palladium $ 359.70 (U.S.) per ounce. The base exchange rate assumed for the economic model is Canadian-dollar/U.S.-dollar equals 0.90.

Processing of the ore is to be by standard grinding and flotation techniques. Most of the comminution test work was by SGS Mineral Services of Lakefield Ontario. Metallurgical recoveries used in the study were based on extensive test work conducted at Process Research Associates in Richmond B.C. under the supervision of F. Wright Consulting Inc. Most of the associated analytical work was performed by iPL Laboratories which has ISO 9001 accreditation with check analyses performed by ACME labs of Vancouver BC. Testwork included both open cycle and locked cycle tests. The predicted plant recoveries of 72% nickel, 81 % copper, 71% cobalt, 47% platinum and 82% palladium were based on a locked cycle test that produced an average concentrate grade of 10.2% nickel, 2.5% copper, 0.36% cobalt 9.8 g/t palladium and 1.5 g/t platinum. This concentrate also contained approximately 33% S, 35% Fe and 5.4% MgO. Smelting and refining charges were based on indicative terms received from a Sudbury smelter and refiner of nickel and associated metals. The report of F.Wright Consulting concluded that "Based on more recent open cycle studies... further improvements to recovery may be available by modifications to the reagent scheme."

Initial capital cost (but not including sustaining capital) for the project including contingency is estimated to be $123 million. Major cost components include plant and infrastructure at $65.6 million; mining equipment at $29.4 million; EPCM and owners costs of $13.2 million; tailings and water management of $4 million and contingency of $10.6 million. The plant and infrastructure was designed for an average throughput of 2,750 tonnes of ore per day. Met-Chem Canada Inc. completed the plant and infrastructure design as well as capital cost and operating costs estimation for the plant. Power will be accessed from the Manitoba Hydro grid.

Baseline environmental studies are well advanced in the project area and the Company will soon commence public engagement for the project leading to a formal permit application. Tailings and water management facilities were designed by Golder Associates Ltd.

Mustang Proceeding with Full Feasibility Study

The Mustang board of directors has approved that a full feasibility study be completed and a mine permit be applied for at the Maskwa Project. Currently additional work at the project is focused on in-pit resource expansion. Mustang has completed drilling additional drill holes in the area of the proposed Maskwa Open Pit and has completed additional sampling of available historical holes. Based on the results of this work a new resource will be calculated for inclusion in the full feasibility study. Mustang will also investigate supplying open pit feed from the Mayville M2 resource to further enhance the economics and mine life of the Maskwa project.

The external Qualified Persons for purposes of National Instrument 43-101 are:

Micon International Inc. - Ian Ward P.Eng, Chris Jacobs C.Eng.

Wardrop Engineering Inc, - Cliff Duke, P.Eng., Chris Sharpe, P.Eng.

Met-Chem Canada Inc.- Lionel Poulin Eng.

F.Wright Consulting Inc. - Frank Wright P. Eng.

Golders Associates Ltd.- Irwin Wislesky, P.Eng.

About Mustang Minerals Corp. - Base Metal Resources

Mustang owns 100% of the mineral rights to Maskwa subject to a 1% Net Smelter Royalty with no obligations for offtake or back-in rights held by a third party. Mustang also owns the mineral rights to the Mayville Property which is located 35 km by road from Maskwa. The geological resource at the Mayville M2 Zone consists of an open pit Indicated Resource of 21.9 million tonnes grading 0.20% nickel and 0.48% copper containing 94.3 million pounds of nickel and 232 million pounds of copper. The M2 resource was prepared by Scott Wilson Roscoe Postle Associates in January 2007. (for technical notes please see Feb.7, 2008 press release).

Carey Galeschuk P. Geo and Ernie Marcotte P. Eng are the Qualified Person for Mustang Minerals Corp. for purposes of National Instrument 43-101.

To find out more about Mustang Minerals Corp. (TSX-V: MUM) visit our website at www.mustangminerals.com or contact: David Black, Investor Relations Telephone (416) 955-4773 email: info@mustangminerals.com

We seek safe harbour.

This news release contains forward-looking statements within the meaning of the United States Private Securities Litigation Reform Act of 1995 and forward-looking information within the meaning of the Securities Act (Ontario) (together, "forward-looking statements"). Such forward-looking statements may include the Company's plans for its mineral projects in Manitoba, the overall economic potential of its properties, the availability of adequate financing and involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements expressed or implied by such forward-looking statements to be materially different. Such factors include, among others, risks and uncertainties relating to potential political risk, uncertainty of production and capital costs estimates and the potential for unexpected costs and expenses, physical risks inherent in mining operations, currency fluctuations, fluctuations in the price of nickel and other metals, completion of economic evaluations, changes in project parameters as plans continue to be refined, the inability or failure to obtain adequate financing on a timely basis, and other risks and uncertainties, including those described in the Company's Management Discussion and Analysis for the period ended December 31, 2007 and Material Change Reports filed with the Canadian Securities Administrators and available at www.sedar.com.

The Company advises investors that although certain terms contained herein are recognized and required by Canadian securities regulations (under National Instrument 43-101 "Standards of Disclosures for Mineral Projects"), the US Securities and Exchange Commission does not recognize these terms.

Shares Outstanding: 72,407,427

SOURCE: Mustang Minerals Corp.

Mustang Minerals Corp. David Black Investor Relations (416) 955-4773 Email: info@mustangminerals.com Website: www.mustangminerals.com
Copyright (C) 2008 Marketwire. All rights reserved.

» zur Grafik
 
ja, Super für Mustang!

9 Mio Pfund Nickel pro Jahr zu Cashcost von ca. 3 $ pro Pfund, das ist hochprofitabel bei den aktuellen Preisen

müßte ja die Tage auch was von tenajon kommen.................. :)
 
Die nächsten top News stehen bei -T5Q- Tenajon und -CRR- Cuervo aus!! :)

>>> Tenajon mit dem NI - Bericht (Update) zum Ajax-Projekt! (laut IR "Anfang Mai erwartet!")

>>> Cuervo mit dem ERSTEN NI - Bericht zum Cerro-Projekt (laut IR "im Mai erwartet!")

Ende Juni folgt -LR8- Largo Resources mit der FINAL Feasibility Studie zum Maracas-Projekt!

Spannende Wochen voraus würde ich sagen..... :up: :whistle:



[url=http://peketec.de/trading/viewtopic.php?p=396422#396422 schrieb:
greenhorn schrieb am 08.05.2008, 11:27 Uhr[/url]"]ja, Super für Mustang!

9 Mio Pfund Nickel pro Jahr zu Cashcost von ca. 3 $ pro Pfund, das ist hochprofitabel bei den aktuellen Preisen

müßte ja die Tage auch was von tenajon kommen.................. :)
 
die Kosten sind leicht gestiegen, ansonsten läuft alles nach Plan - wenn ich das richtsch lese

May 08, 2008 07:30 ET
Crowflight Provides Bucko Lake Nickel Project Update
TORONTO, ONTARIO--(Marketwire - May 8, 2008) - CROWFLIGHT MINERALS INC. (Crowflight, the Company) (TSX VENTURE:CML) today provided a project update for the Bucko Lake Nickel Project (Bucko) that is currently under development outside Wabowden, Manitoba.

Surface Facilities

Work is progressing steadily on the surface facilities at Bucko, with much of the current activity focused on the processing plant. Most of the processing plant equipment is on-site, with some electrical components due to arrive in the next two months. The jaw and cone crusher are in place with structural steel for the crushing circuit progressing. The conveyors are on-site and the conveyor sections should be installed between now and June. Installation of the fine ore bin is expected to begin shortly. Mechanical installation of the rod and ball mill is close to completion, as is the mechanical installation of the flotation circuit. The concentrate filter is in place, electrical work on the plant's interior has begun and piping is expected to start shortly.

In addition to work on the processing plant, the area for the Interim Tailings Storage Facility (ITSF) has been cleared and the geotechnical and design work is complete.

Underground Development

The new portal for the underground ramp is progressing with completion expected by the end of May.

Two diamond drills are currently underground undertaking definition and delineation drilling on the 1,000 foot level. It is expected that the geotechnical information and assay results from this drilling should assist in optimizing the geotechnical design and upgrading the mineable reserve. The development underground on the 1,000 foot level has progressed to the point that the larger mining equipment is ready to be transported underground and then assembled to finish the remaining work on that level and the ramps to other levels.

Paul Keller, Crowflight's VP of Operations and COO, said: "A tremendous amount of progress has been made at Bucko since beginning construction in November 2006. Our staff, contractors and consultants have been working tirelessly to bring Bucko into production in the third quarter of 2008 and we look forward to achieving this goal."

The operating costs, including on-site and off-site costs, are projected to be $4.32 per pound of nickel produced, using a US$:Cdn$ exchange rate of 1:1.The capital cost for the Bucko Lake Nickel Deposit development is now expected to be Cdn$86 million net of pre-production revenue, assuming a US$:Cdn$ exchange rate of 1:1. This compares to the Feasibility Study estimate of Cdn$66.0 million at an exchange rate of 0.8:1.

The cost differences are attributable to the following: Cdn$6.7 million due to capital development timing, the addition of the ITSF, the ramp portal and surface connection to the underground internal ramp; Cdn$3.0 million for increased surface infrastructure EPCM (Engineering Procurement and Construction Management); and Cdn$10.5 million for additional processing plant equipment, foreign exchange differences and increased structural steel and concrete foundation costs.

The inclusion of the ramp portal, the ITSF and additional processing plant equipment, which will enable the processing plant to process up to 1,500 tonnes of ore per day, were not included in the original scope of the Feasibility Study. The ramp connection to surface will open new production areas sooner in the life-of-mine schedule and will provide operational flexibility. The addition of the ITSF is necessary to begin operations in 2008 due to delays in the federal permitting of Bucko Lake as a tailings storage facility (see Press Release dated March 28, 2008).

Mike Hoffman, Crowflight's President and CEO, said: "One striking advantage of Bucko compared to other mining projects currently being developed throughout the world is that the overall capital costs are moderate in relation to future expected cash flow, especially considering that nickel prices have recently averaged US$12-14 per pound. Many of the cost increases are attributable to scope changes not included in the original Feasibility Study and are designed to add further value to the Bucko Project. These enhancements are necessary to tap into the further potential we believe exists at Bucko. Some of the other cost increases, such as steel and concrete, are consistent with those of other companies currently building mines."

During 2007, Cdn$35.3 million was spent on Bucko construction, which includes the main electrical installation, hoist and headframe installation, processing plant foundations and steel, shaft de-watering and rehabilitation, rehabilitation of the 1000 Level exploration drift, purchasing new and used equipment, refurbishing used equipment and EPCM to date.

Additional information, including Crowflight's Financial Statements and Management Discussion and Analysis, can be found electronically on the System for Electronic Document Analysis and Retrieval ("SEDAR") through Crowflight's profile at www.sedar.com.

The current construction schedule estimates that the commissioning of the processing plant will occur in July and August of 2008, with cash flow from concentrate sales beginning shortly thereafter. Full commercial production is expected in early 2009.

Crowflight Minerals - Canada's Next Nickel Producer

Crowflight Minerals Inc. (TSX VENTURE:CML) is a Canadian junior mining exploration and development company focused on nickel, copper and Platinum Group Mineral (PGM) projects in the Thompson Nickel Belt and Sudbury Basin. The Company currently owns and/or has under option approximately 800 square kilometres of exploration and development properties in Manitoba and Ontario.

Crowflight's priority is to bring the fully-funded Bucko Lake Nickel Project located near Wabowden, Manitoba into production by the third quarter of 2008.
 
:bye: Schöne Pfingstfest euch !!!! :friends: :beer:
 
Danke green!!! Wünsche ich Dir auch! :friends:

[url=http://peketec.de/trading/viewtopic.php?p=396836#396836 schrieb:
greenhorn schrieb am 08.05.2008, 18:02 Uhr[/url]"]:bye: Schöne Pfingstfest euch !!!! :friends: :beer:
 
CUERVO REPORTS WITHDRAWAL OF PRIVATE PLACEMENT


May 9, 2008 – Toronto, ON


Cuervo Resources Inc. (CNQ-IRON; FWB-CRR; “Cuervo” or the “Company”) reports that, it has withdrawn the previously planned private placement of equity units in the Company due to market conditions.

Cuervo common shares are listed on the Canadian Trading and Quotation System Inc. (CNQ), as well as the Frankfurt Stock Exchange. Currently, there are 26,629,750 shares outstanding (33,556,000 fully diluted).

For further information, please contact Mr. John Siriunas, a director and President of Cuervo, at (416) 203-3957 x701 or Mr. Tom Berner, Investor Relations, at (416) 203-3957 x202. Additional information about Cuervo can be found at the Company’s website at www.cuervoresources,com.

The Canadian Trading and Quotation System Inc. has neither approved nor disapproved of the contents of this press release.
 
Hi Duke - dein Näschen bei TVC (Tournigan) mal wieder Spitze! :up:

May 09, 2008 16:02 ET
Bluerock Resources Ltd. Announces Non-Brokered Private Placement
VANCOUVER, BRITISH COLUMBIA--(Marketwire - May 9, 2008) -

NOT FOR DISSEMMINATION IN THE UNITED STATES OR VIA US NEWSWIRE SERVICES

Bluerock Resources Ltd. (TSX VENTURE:BRD) (the "Company") announces a non-brokered private placement to issue up to 5,400,000 units to raise up to C$2,700,000 (the "Offering") with a 10% overallotment.

Each unit will be priced at $0.50 and will consist of one common share and one half transferable share purchase warrant. Each full warrant will entitle the holder to purchase one additional common share, exercisable for one year from the closing date, at a price of $0.85 per share. A 5% finders fee will be payable in association with part the financing.

The Company will use the private placement funds to further the development of its Colorado mining projects to develop uranium production in order to take full advantage of toll milling capacity reserved for Bluerock Resources in our toll milling agreement with Denison Mines (USA) described in our press release of January 16, 2008.

Bluerock Resources Ltd. is a uranium mining company focused on developing tomorrow's energy today through the acquisition and development of conventional uranium resources in Utah and Colorado.

ON BEHALF OF THE BOARD OF DIRECTORS

Michael Collins, CEO, President and Director
 
wie iss deine Meinung zu den verstärkten Käufen des Managments bei BVG - Bravo?
aus Erfahrung iss sowas ja sehr oft ein gutes Zeichen und zusätzlich absolut ausgebombter Chart - so wie auch AQA...
 
[url=http://peketec.de/trading/viewtopic.php?p=397683#397683 schrieb:
greenhorn schrieb am 12.05.2008, 09:46 Uhr[/url]"]wie iss deine Meinung zu den verstärkten Käufen des Managments bei BVG - Bravo?
aus Erfahrung iss sowas ja sehr oft ein gutes Zeichen und zusätzlich absolut ausgebombter Chart - so wie auch AQA...

Im Moment peile ich verstärkt auf Cuervo. Der Chef hat im Dez. auch gekauft.(gutes Zeichen)
Abgesagtes PP.

Möglichkeit: Übernahme,strategische Beiteiligung, Druck um das Projekt zu hegdgen und bessere Konditionen im PP zu erwirken.
Transportstudie war ja positiv!
 
dachte immer das ein abgesagtes PP nich janz soooo jut iss?! :scratch:
 
:)by the Way: - abgesehen sicher von der Vewässerung - ein sehr guter Preis, genau wie bei Largo ein PP deutlich über Marktpreis:


Tenajon Resources 7.5-million-share private placement


2008-05-09 16:26 ET - Private Placement

The TSX Venture Exchange has accepted for filing documentation with respect to a brokered private placement announced April 29, 2008.


Number of shares: 7.5 million shares

Purchase price: 55 cents per share

Hidden placees: 13

Insiders: D. Bruce McLeod, 50,000; Donald McLeod, 90,900

Agents' fees: $156,887.50 and 262,500 broker warrants payable to Canaccord Capital Corp.; $65,931.25 and 131,250 broker warrants payable to Blackmont Capital Inc.; $65,931.25 and 131,250 broker warrants payable to Dundee Securities Corp.
 
[url=http://peketec.de/trading/viewtopic.php?p=397735#397735 schrieb:
greenhorn schrieb am 12.05.2008, 11:19 Uhr[/url]"]dachte immer das ein abgesagtes PP nich janz soooo jut iss?! :scratch:

Im Prinzip ja, nur es gibt keine News, die das ausser Taktik begründen. PP Preis 1,50 CAD plus Warrant.
 
Möglichkeit das niemand Geld geben will? iss sicherlich nicht so schlüßig da das Projekt ja sehr gut iss :scratch:
was mich bei Cuervo ein wenig "stört" ist der Börsenplatz.....so schlecht nachzuvollziehen!
[url=http://peketec.de/trading/viewtopic.php?p=397739#397739 schrieb:
dukezero schrieb am 12.05.2008, 11:22 Uhr[/url]"]
[url=http://peketec.de/trading/viewtopic.php?p=397735#397735 schrieb:
greenhorn schrieb am 12.05.2008, 11:19 Uhr[/url]"]dachte immer das ein abgesagtes PP nich janz soooo jut iss?! :scratch:

Im Prinzip ja, nur es gibt keine News, die das ausser Taktik begründen. PP Preis 1,50 CAD plus Warrant.
 
Transportstudie positiv,NI Resourcenschätzung 2 Q 2008,Chef kauft,Börsenplatz sollte auch gewechselt werden.
[url=http://peketec.de/trading/viewtopic.php?p=397740#397740 schrieb:
greenhorn schrieb am 12.05.2008, 11:24 Uhr[/url]"]Möglichkeit das niemand Geld geben will? iss sicherlich nicht so schlüßig da das Projekt ja sehr gut iss :scratch:
was mich bei Cuervo ein wenig "stört" ist der Börsenplatz.....so schlecht nachzuvollziehen!
[url=http://peketec.de/trading/viewtopic.php?p=397739#397739 schrieb:
dukezero schrieb am 12.05.2008, 11:22 Uhr[/url]"]
[url=http://peketec.de/trading/viewtopic.php?p=397735#397735 schrieb:
greenhorn schrieb am 12.05.2008, 11:19 Uhr[/url]"]dachte immer das ein abgesagtes PP nich janz soooo jut iss?! :scratch:

Im Prinzip ja, nur es gibt keine News, die das ausser Taktik begründen. PP Preis 1,50 CAD plus Warrant.
 
hast du einen Link zur Heimatbörse von Cuervo?
 
http://www.cnq.ca/Page.asp?PageID=2013&AA_RecordID=180&SiteNodeID=203


[url=http://peketec.de/trading/viewtopic.php?p=397752#397752 schrieb:
greenhorn schrieb am 12.05.2008, 11:45 Uhr[/url]"]hast du einen Link zur Heimatbörse von Cuervo?
 
:danke: Olli
 
staune auch , solche Stücke an einem Feiertag.............
[url=http://peketec.de/trading/viewtopic.php?p=397773#397773 schrieb:
Ollinho schrieb am 12.05.2008, 12:08 Uhr[/url]"]B6I sieht verdammt gut aus!!! :up:
[url=http://peketec.de/trading/viewtopic.php?p=397771#397771 schrieb:
greenhorn schrieb am 12.05.2008, 12:06 Uhr[/url]"]:danke: Olli
 
May 12, 2008 08:00 ET
Mustang Drilling at East Bull
TORONTO, ONTARIO--(Marketwire - May 12, 2008) - Mustang Minerals Corp.(TSX VENTURE:MUM)(FRANKFURT:NJF) today announced that it has commenced drilling and has encountered mineralization at the East Bull Lake Property west of Sudbury Ontario. The Company is targeting platinum group metals-nickel-copper mineralization at the Property. A program of 1,000 meters of diamond drilling is planned in the first phase.

Mustang has held unpatented mining claims through option agreements covering the East Bull Lake Intrusion since 1998. The East Bull Lake Property has been the source of considerable fieldwork and drilling by Mustang and other exploration companies as well as work completed by the Ontario Geological Survey. Previous work by Mustang has concentrated primarily on disseminated platinum group metal mineralization along the contact of the intrusion. A 1993 Ontario Geological Survey Report (Open File Report 5849. Peck, James Chubb et al) concluded that the "potential exists for extremely large tonnages of sulphide mineralization, perhaps even massive sulphides (along the floor of the intrusion), which have platinum-group element-enrichment levels equating to reef environments."

Mustang completed a Geotech VTEM heliborne geophysical survey over the East Bull Lake Property in 2007. In March 2008 Mustang had geophysical analysis and interpretation of the VTEM data completed, supervised by Caracle Creek Consulting of Sudbury Ontario. The interpretation of the VTEM data identified several priority targets for drilling including several large deep seated EM conductors which are of interest in light of the geological target of sulphide accumulations along the margins of the intrusion.

The current program will target a geophysical VTEM conductor located near an area of near surface mineralization at the Parisien Lake Deformation Zone ("PLDZ"). The VTEM targets coincide with targets generated by a ground IP survey previously completed by Mustang but which were not previously drilled. Maximum metal concentrations noted in Open File Report 5849 collected from forty-three select grab samples of sulphide mineralization from surface exposures at the PLDZ contained maximum 2890 ppb Palladium, 1060 ppb Platinum, 860 ppb Gold, 14.5% copper and 1.6% nickel.

Multiple meter scale bands of disseminated mineralization were encountered in the second hole of the present drill program. Also present in the core was net textured sulphides and a meter of massive sulphide. Assays will be reported as soon as possible from the program. Additional information about East Bull and photographs of the mineralized drill core are available at www.mustangminerals.com.

Rationale

Mustang views the East Bull Lake Property as a high potential property for platinum group metals, nickel and copper. This view is based on academic work completed on the East Bull Lake Property by the Ontario Geological Survey, exploration results demonstrating a well mineralized layered intrusion and interest in the property from major mining companies in the past.

A recently completed VTM airborne geophysical survey has identified new drill targets within the intrusion that could represent the accumulation of massive sulphides along the margins of the intrusion. Mustang is of the view these high potential targets should be drill tested as they are part of a series of broad VTEM conductors that could possibly represent semi-massive to massive sulphide accumulations along the margins of the intrusion.

After completion of exploration drilling targeting the near surface target at the PLDZ Mustang intends to find a joint venture partner to fund a significant drill program to test the deeper targets at East Bull.

Mustang's priority both for project development and exploration remains its Manitoba properties notably the Maskwa Nickel Project where a prefeasibility study has recently been released. Drill results from several "blue sky" exploration holes at Maskwa are pending.

Carey Galeschuk P. Geo is the Qualified Person for Mustang Minerals Corp. for purposes of National Instrument 43-101. Joerg Kleinboeck P.Geo., a consultant with Caracle Creek International Consulting Inc., will be supervising the drilling program.




To find out more about Mustang Minerals Corp. (TSX-V:MUM) visit our website at www.mustangminerals.com or contact: David Black, Investor Relations Telephone 416-955-4773 email: info@mustangminerals.com
 
ITH Commences 42,000 Metre Resource Drilling Program at the Livengood Gold Project, Alaska

VANCOUVER, BRITISHCOLUMBIA--(Marketwire - May 12, 2008) - International Tower Hill MinesLtd. ("ITH" or the "Company") - (TSXVENTURE:ITH)(AMEX:THM)(FRANKFURT:IW9) is pleased to announce the startof resource expansion drilling at the Livengood Gold Project. TheCompany plans to drill approximately 42,000 metres in 150-175 holeswithin the core target area, which covers an area of approximately 1.5square kilometres. The resource expansion program will focus on thehigher-grade Lillian Zone of the deposit and is designed to double thesize of the 2.0M ounce inferred gold resource (87.8 Mt at a grade of0.71 g/t using a 0.50 g/t gold cutoff) (See NR-08-06) which iscontained within the global inferred resource of 3.3 M ounces of gold(188 Mt at a grade of 0.54 g/t gold using a 0.30 g/t gold cutoff)(Figure 1). The Lillian Zone has returned a number of higher gradeintervals such as 8.8 metres of 9.95 g/t gold, 8.5 metres of 9.64 g/tgold and 3.5 metres @ 7.33 g/t gold contained within thick (greaterthan 50 metre) intervals averaging above 1 g/t gold.

The grade-tonnage curve produced from the initial resourcecalculation using 48 drill holes indicates there is a significantpotential to define a large resource at Livengood. With just 25% of thecore target area drilled to date, the Company considers that the upsidepotential for the deposit is enormous. Readers are cautioned thatmineral resources which are not mineral reserves do not havedemonstrated economic viability. The estimate of mineral resources maybe materially affected by environmental, permitting, legal, marketing,or other relevant issues.

To view Figure 1: Livengood grande tonnage curve for initial inferred resource, please view the following link: http://media3.marketwire.com/docs/fig1livengoodgradetonnagecurve.pdf.

The drill program, which is expected to continue until December2008, will utilize two large reverse circulation drills and one coredrill operating 24 hours per day seven days a week. The plan is to griddrill an area of roughly 2 kilometres by 800 metres, with a nominaldrillhole spacing of 75 metres. The program will test both the volcanichosted and higher grade sediment hosted targets within the mainstructural corridor (Figure 2).

Mineralization outcrops at the surface and extends to the currentdepth of drilling (approximately 250 metres), with an average of 30% ofall holes mineralized above the 0.25 g/t gold cutoff grade. Inaddition, the Company has also begun baseline environmental studies aswell as an expanded metallurgical program to better characterize theprimary ore types in the Livengood deposit.

To ensure the efficient and effective development of the Livengooddeposit, the Company has hired Mr. Robert Butts as project manager. Mr.Butts was instrumental in working with Mr. Pontius during the discoveryand development of the Cripple Creek deposit in Colorado. Cripple Creekis a large low-grade bulk tonnage deposit, which has now exceeded 15Mounces of gold in combined production and resource.

Jeffrey Pontius, President and CEO of ITH, stated "We are veryexcited to move the Livengood deposit to this next stage of developmentas this type of opportunity to define a major new gold deposit in sucha logistically and politically favourable location is very rare".

To view Figure 2: Outline of Lillian Zone (Red Box) 2008 grid drill area, Livengood Project, please view the following link: http://media3.marketwire.com/docs/fig2outlineoflillianzone.pdf.

Livengood Project Overview

The Livengood project is 100% owned by ITH. It is located 100kilometres north of Fairbanks, Alaska on the all weather paved ElliotHighway which provides year round access and excellent logistics. Theproject is 80 kilometres north of the Fort Knox Mine, Alaska's largestgold mine.

Drilling in 2006 and 2007 by the Company at Livengood has shownthat the gold mineralization is hosted primarily in a sequence ofDevonian sediments and volcanics. These units represent favourablehosts and are pervasively mineralized throughout the core project area.The gold mineralization at Livengood is believed to be related to a90Ma Cretaceous magmatic event and would therefore be part of theregional Mid Cretaceous mineralizing event which produced the PogoDeposit (5M ounces of gold) and the Fort Knox deposit (10M ounces ofgold). Initial gold recovery tests indicate that the bulk of themineralization encountered to date is highly amenable to cyaniderecoveries (NR-08-06).

Qualified Person

Jeffrey A. Pontius (CPG 11044), a qualified person as defined byNational Instrument 43-101, has supervised the preparation of thescientific and technical information that forms the basis for this newsrelease. Mr. Pontius is not independent of the Company, as he is thePresident and CEO.

Qualified Person and Quality Control/Quality Assurance

The work program at Livengood has been designed and is supervisedby Dr. Russell Myers, Vice President of Exploration, Talon Gold (US)LLC (a wholly owned subsidiary of ITH responsible for carrying out theCompany's exploration programs), who is responsible for all aspects ofthe work, including the quality control/quality assurance program.On-site personnel at the project photograph core from each individualborehole prior to preparing the split core. Duplicate reversecirculation samples are collected with half remaining on site and halfbeing sent for analysis. Representative chips are kept for reference.All samples are tracked using barcodes to minimize errors. Sampleshipments are sealed on site and shipped to ALS Chemex for assay. ALSChemex's quality system complies with the requirements for theInternational Standards ISO 9001:2000 and ISO 17025:1999. Analyticalaccuracy and precision are monitored by the analysis of reagent blanks,reference material and replicate samples. Quality control is furtherassured by the use of international and in-house standards. Finally,representative blind duplicate samples are forwarded to ALS Chemex andan ISO compliant third party laboratory for additional quality control.

About International Tower Hill Mines Ltd.

International Tower Hill Mines Ltd. is a resource explorationcompany, focused in Alaska and Nevada, which controls a number ofexploration projects representing a spectrum of early stage to advancedgold discoveries. ITH is committed to building shareholder valuethrough new discoveries while maintaining a majority interest in itskey holdings, thereby giving its shareholders the maximum value fortheir investment.

On behalf of INTERNATIONAL TOWER HILL MINES LTD.

Jeffrey A. Pontius, President and Chief Executive Officer
 
May 12, 2008 10:01 ET
Osisko Closes $20 Million Unsecured Debt Financing
MONTREAL, QUEBEC--(Marketwire - May 12, 2008) - Osisko Exploration Ltee (TSX:OSK)(FRANKFURT:EWX) is pleased to announce that it has closed its previously announced agreement with Solidarity Fund QFL (the Fund) for a $20 million unsecured debt financing having a seven-year term. The debt will carry 9.5% interest, payable in shares or cash prior to commercial production and in cash thereafter. Principal will be repaid in a minimum of 48 equal installments commencing on the earlier of commercial production of the Canadian Malartic Project or 36 months from closing.

The Company also granted the Fund 1,100,000 warrants exercisable within 60 months at a price of $7.46. The Company may accelerate the exercise of warrants if Osisko's shares trade at a significant premium to the exercise price during the term of the warrants.

Sean Roosen, President & CEO of Osisko, commented: "We are extremely pleased with the Fund's financial participation in the Canadian Malartic Project. Our gold project will have a significant impact on the Abitibi economy and it is anticipated that 400 jobs will be created over a period of at least 15 years."

About Osisko

Osisko Exploration Ltee is currently evaluating the Canadian Malartic gold deposit and adjacent areas for a large-scale open pit, bulk-tonnage mining operation. The Company is well-funded with approximately $170 million on hand and is carrying out an aggressive definition drilling and exploration campaign on the Canadian Malartic deposit and surrounding properties.

About the Solidarity Fund QFL

With net assets of over $7.4 billion as at November 30, 2007, the Solidarity Fund QFL is a development capital company that through its RRSP channels the savings of Quebecers into investments in all sectors of the economy to help create and maintain jobs and to further Quebec's economic growth. The Fund is a partner, either directly or through its network members, in 1,696 companies. It currently has more than 575,000 shareholders and has helped, on its own or with other financial partners, to create, maintain and protect over 122,000 jobs. For more information, visit www.fondsftq.com
 
Status
Für weitere Antworten geschlossen.
Oben Unten